A leading global technology enterprise engaged Introl for a comprehensive, greenfield data center deployment in Frankfurt, Germany. The client required a fully equipped, high-performance data center designed to support substantial future growth and rapidly evolving technical demands within Europe.

Project Scope

Data center with rows of server racks, white cabinets, and yellow cable management overhead

Introl was entrusted with delivering an extensive, end-to-end infrastructure solution, including:

  • Installation of 50 server cabinets.

  • Comprehensive structured cabling system integrating both copper and fiber optic solutions.

  • High-density fiber deployment, featuring 96 strands terminated at the top of each cabinet.

  • Copper structured cabling providing 24 ports per rack for immediate connectivity and flexibility.

  • Complete rack-and-stack services for servers and network switches.

  • Dual redundant Power Distribution Units (PDUs) installed per rack.

  • Advanced hot aisle containment solutions for optimal cooling efficiency.

Technical Execution

The project required detailed planning, precision execution, and close coordination, delivered through multiple critical phases:


Infrastructure Deployment:

  • Detailed initial site surveys, layout design, and precise space utilization planning.

  • Deployment of 50 high-quality server cabinets configured for optimal airflow and power distribution.


Structured Cabling Installation:

  • Installation of high-performance OM4 MTP fiber optic cables, terminated with 96 strands per cabinet, providing high bandwidth and scalability.

  • Deployment of CAT6A copper cabling infrastructure, configured to provide 24 ports per rack, meeting immediate and future connectivity demands.

  • Efficient cable management using overhead cable trays, structured pathways, and advanced labeling for simplified ongoing maintenance.


Rack-and-Stack Operations:

  • Precise installation and secure stacking of servers and switches in accordance with detailed equipment specifications.

  • Comprehensive documentation, including hardware inventory, asset tags, and serial number records.

  • Expert patching, with meticulous labeling and documentation to ensure ease of ongoing management.


Power and Cooling Infrastructure:

  • Installation of dual redundant PDUs per rack to ensure uninterrupted power delivery.

  • Implementation of advanced hot aisle containment, enhancing cooling efficiency, improving airflow management, and significantly reducing operational costs.


Technical Challenge and Solution

During the structured cabling phase, the team encountered an unexpected technical issue. After preliminary testing, it was discovered that the client’s network switches were incompatible with the initially specified fiber optic transceivers, leading to significant signal loss.

To resolve this swiftly and maintain the original project timeline, Introl's technical team promptly:

Conducted detailed diagnostic testing and identified the root cause of the incompatibility.

  • Sourced and procured compatible transceivers rapidly, leveraging vendor relationships to expedite delivery.

  • Implemented round-the-clock shifts with expert technical support to replace the transceivers systematically and efficiently.

  • Carried out rigorous validation tests post-installation to guarantee optimal performance and reliability.

Through these decisive actions, Introl overcame the unforeseen compatibility issue with minimal impact on the overall project schedule, demonstrating remarkable responsiveness and technical proficiency.

A white delivery van with the 'introl' logo parked in front of a warehouse building with closed garage doors, surrounded by a paved area and some greenery.

Project Timeline and Delivery

Close-up of a male construction worker with a beard wearing a white safety helmet and reflective safety vest, smiling.

Introl deployed an expert team of technicians and engineers, successfully executing the comprehensive installation over an aggressive eight-week period:

Weeks 1-2: Cabinet installation, cable tray assembly, and backbone cabling.

Weeks 3-4: Fiber optic and copper cable deployment, terminations, and preliminary testing.

Weeks 5-6: Identification and resolution of compatibility issues with fiber optic transceivers.

Weeks 7-8: Server and switch rack-and-stack, PDU configuration, hot aisle containment installation, and final system performance validations.

Results and Client Benefits

The Frankfurt data center project was completed successfully, delivering immediate and lasting benefits:

  • Enhanced scalability and infrastructure density, effectively accommodating future growth.

  • Superior operational reliability through meticulous cable management, redundant power, and advanced containment solutions.

  • Improved energy efficiency, airflow management, and reduced operational costs.

  • Detailed documentation and labeling, facilitating streamlined management and maintenance.

A woman in a hard hat and safety vest standing in a server room with racks of server equipment in the background.

Client Feedback

The client commended Introl’s professionalism, agility, and technical expertise, particularly praising the rapid resolution of the transceiver compatibility issue. The client expressed high satisfaction with the timely and high-quality delivery of the project.

Conclusion

Technician in hard hat and vest working in server room with cables

Introl’s successful execution of the Frankfurt data center installation, including navigating complex technical challenges efficiently, underscores its capability to deliver sophisticated infrastructure solutions tailored to meet the demanding needs of leading global enterprises.