PJM's $100 Billion Rate Shock: How Data Centers Are Rewriting America's Electricity Bills
Feb 28, 2026 Written By Blake Crosley
PJM Interconnection's capacity auction cleared at $329.17 per megawatt-day for the 2026-2027 delivery year, a price that would have seemed fictional two years earlier.1 In the 2024-2025 auction, generators accepted $28.92/MW-day to keep the lights on for 67 million people across 13 states and Washington, D.C.2 The roughly tenfold increase landed squarely on ratepayers, and data center demand drove 63% of it.3 Cumulative costs through 2033 could reach $100 billion to $163 billion, depending on whether price caps hold.45 The average family in PJM territory faces an estimated $70-per-month increase by 2028.6 State legislators from Virginia to Oregon have responded with a wave of rate reforms, tax incentive rollbacks, and construction moratoriums that will reshape data center economics for at least the next decade.
TL;DR
PJM capacity prices surged from $28.92/MW-day (2024-2025) to $329.17/MW-day (2026-2027), hitting the FERC-approved price cap for two consecutive auctions. Data centers caused 63% of the price increase in the 2025-2026 auction, adding $9.3 billion in capacity costs that all ratepayers must absorb. NRDC estimates $100 billion to $163 billion in cumulative costs through 2033 unless regulators intervene. Oregon became the first state to create a dedicated data center rate class. Virginia's SB 253 would shift distribution and capacity costs from households to data centers. At least six states have introduced construction moratoriums, and seven states have moved to repeal or restrict data center tax incentives worth billions annually.
The PJM Price Explosion: A Three-Year Timeline
PJM Interconnection operates the largest wholesale electricity market in North America, coordinating power delivery for 65 million customers across Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, West Virginia, and the District of Columbia.7
The capacity market ensures generators remain available to meet future demand. Utilities purchase capacity credits through annual auctions, and those costs flow directly into household electricity bills. The last three auctions tell a story of exponential cost escalation:
PJM Capacity Auction Price History
| Delivery Year | Clearing Price ($/MW-day) | Year-over-Year Change | Key Driver |
|---|---|---|---|
| 2020-2021 | $76.53 | Baseline | Normal market conditions |
| 2021-2022 | $140.00 | +83% | Post-pandemic recovery |
| 2022-2023 | $50.00 | -64% | Excess capacity |
| 2023-2024 | $34.13 | -32% | Continued surplus |
| 2024-2025 | $28.92 | -15% | Market trough |
| 2025-2026 | $269.92 | +833% | Data center demand surge |
| 2026-2027 | $329.17 | +22% | Price cap reached |
| 2027-2028 | $333.44 | +1.3% | Price cap reached again |
Sources: PJM Interconnection BRA Reports8; IEEFA analysis9; Utility Dive10
The 2025-2026 auction delivered the sharpest single-year increase in PJM's 27-year capacity market history: an 833% jump from $28.92 to $269.92/MW-day.11 The 2026-2027 auction hit the FERC-approved price cap of $329.17/MW-day, and the December 2025 auction for 2027-2028 hit the updated cap of $333.44/MW-day while falling 6,625 MW short of reliability requirements for the first time ever.1213
PJM's Independent Market Monitor calculated that the existing price cap already prevented $13 billion in additional capacity costs from reaching ratepayers.14 Without the cap, clearing prices could have exceeded $500/MW-day.15
Who Pays and How Much
The cost transmission mechanism from capacity auction to household bill involves no buffer. Utilities purchase capacity at auction, regulators approve cost recovery through rate cases, and customers absorb the full amount.16
Regional Cost Impact
The $9.3 billion in data center-driven capacity costs for the 2025-2026 delivery year spread unevenly across PJM's footprint.17 Data centers account for 40% of total PJM capacity costs in the most recent auction, and the Dominion Energy zone in Virginia faces capacity fees 65% higher than the rest of the grid.1819
Residential customers in western Maryland already pay approximately $18 more per month in PJM capacity costs.20 Ohio residents pay roughly $16 more monthly.21 Across seven mid-Atlantic states, utilities assigned $4.3 billion in data center connection costs to ratepayers in 2024 alone.22
The NRDC Projection
NRDC's analysis of PJM forecasts projects cumulative capacity costs of $163 billion from 2028 through 2033 if the temporary price cap expires as scheduled, translating to an annual capacity bill of $27 billion to $30 billion per year during that window.23 Synapse Energy Economics produced a more conservative estimate of approximately $100 billion through 2033, assuming some form of price mitigation remains in place.24 Both figures dwarf historical norms. Before the data center demand surge, PJM's annual capacity costs averaged roughly $8 billion to $10 billion.25
Delaware's Division of the Public Advocate called the situation urgent enough to petition PJM on January 30 for an extension of the price cap beyond its current expiration.26 PJM agreed on February 12 to seek an extension for the next two auction cycles.27
The Supply-Demand Gap
The price explosion reflects a structural supply-demand imbalance that PJM's own forecasts show worsening through at least 2030:
| Metric | Value | Source |
|---|---|---|
| Projected peak demand growth (2024-2030) | 32 GW | PJM Long-Term Load Forecast28 |
| Data center share of that growth | 94% (30+ GW) | PJM Long-Term Load Forecast29 |
| New data center demand added annually | 5-7 GW | PJM forecast30 |
| New generation supply added annually | 2-3 GW | PJM forecast31 |
| 2027-2028 auction shortfall | 6,625 MW | PJM BRA Report, Dec 202532 |
| Installed reserve margin achieved | 14.8% | PJM BRA Report (target: 20%)33 |
PJM procured 134,479 MW of generation resources in the December 2025 auction against a 141,101 MW reliability requirement.34 The 5.2% shortfall marked the first time in PJM's history that a capacity auction failed to meet the installed reserve margin target.35
The State Legislative Response
Legislators across both parties have introduced more than 238 data center-related bills in all 50 states during 2025, enacting over 40 in 21 states.36 The 2026 session has accelerated the pace. Three categories of legislation dominate: rate structure reform, tax incentive rollbacks, and construction moratoriums.
Rate Structure Reform: Making Data Centers Pay Their Share
Oregon's POWER Act (HB 3546)
Oregon became the first state to create a dedicated data center electricity rate class when the legislature passed the Protecting Oregonians With Energy Responsibility (POWER) Act with bipartisan support in June 2025.37 The law applies to facilities consuming more than 20 MW and requires:
- 10-year minimum contracts committing large energy users to a baseline demand payment regardless of actual consumption38
- Separate cost allocation so data center infrastructure investment does not subsidize residential rate increases39
- Transmission cost pass-through requiring large users to pay for grid upgrades they trigger40
- Biennial PUC reporting beginning September 1, 2026, reviewing load growth trends and ratepayer impacts41
Portland General Electric currently charges large industrial users approximately $0.08/kWh.42 The Oregon Public Utility Commission will determine the new data center rate, which analysts expect will exceed current industrial tariffs given the flat, 24/7 load profile data centers maintain.43
Oregon's Citizens' Utility Board championed the legislation, framing the issue directly: data centers run at peak demand constantly, and existing rate structures never anticipated that load pattern at scale.44
Virginia's SB 253
Virginia Senator L. Louise Lucas introduced an amendment to Senate Bill 253 that would shift distribution and PJM capacity auction costs from residential customers to data centers drawing 25 MW or more.45 The State Corporation Commission estimated a 3.4% residential rate reduction (approximately $5.52/month savings) and a 15.8% data center rate increase.46 Dominion Energy supports the bill.47 (For a deep analysis of SB 253's mechanics and implications, see our full coverage: Virginia SB 253: The Bill That Could Reshape Data Center Economics Nationwide.)
Other State Rate Actions
At least a dozen states, led by both Republican and Democratic lawmakers, have targeted data centers with separate, higher electric rates or required long-term financial commitments before approving grid infrastructure investments for new facilities.48
Oklahoma Republican state senator Brad Boles introduced a ratepayer protection bill requiring data center operators to cover their proportional share of infrastructure costs rather than socializing them across all customers.49 Virginia regulators approved a new GS-5 rate class in November 2025 establishing 14-year mandatory contracts for data centers above 25 MW, with minimum demand charges at 85% of contracted capacity.50
Tax Incentive Rollbacks: The $1.6 Billion Question
Thirty-seven states currently offer data center tax incentives.51 The original economic rationale assumed modest fiscal costs and substantial job creation. The actual numbers have diverged dramatically from projections.
State-by-State Tax Incentive Status
| State | Annual Tax Incentive Cost | Original Estimate | Status (Feb 2026) |
|---|---|---|---|
| Virginia | $1.6 billion (FY2025) | $1.5 million | Reform bills pending; crossover deadline Feb 1852 |
| Georgia | $625 million (FY2026) | $10 million (2020) | Senate passed suspension bill; Governor vetoed repeal in 202453 |
| Michigan | $90 million+ (through 2065) | Not disclosed | Bipartisan repeal bill introduced Dec 202554 |
| South Carolina | $43 million | N/A | Under review55 |
| Indiana | Undisclosed | N/A | Transparency legislation introduced56 |
Sources: Cardinal News57; Georgia Dept. of Audits58; Bridge Michigan59; MultiState60
Virginia's tax incentive story stands out for the sheer gap between projection and reality. When the Commonwealth enacted data center sales and use tax exemptions in 2010, fiscal analysts estimated annual costs of approximately $1.5 million.61 By fiscal year 2025, actual foregone revenue reached $1.6 billion, a 118% increase over the prior year and a 106,000% overshoot of the original estimate.62 Bills HB 897, SB 393, and HB 784 propose new energy standards, additional taxes, and increased transparency, though observers expect the legislature to focus on disclosure requirements rather than outright repeal during the current session.63
Georgia's exemptions jumped from $10 million in 2020 to $625 million in 2026.64 The Georgia Senate passed a bill to suspend future data center tax exemptions, though Governor Brian Kemp vetoed a full repeal bill in 2024, citing business climate concerns.65 Seven separate bills targeting data centers advanced in the 2026 Georgia session, covering tax repeal, residential ratepayer protections, and construction moratoriums.66
Michigan's repeal effort bridged the political spectrum in ways that defied traditional coalitions. State Representatives Jim DeSana (R-Carleton) and Dylan Wegela (D-Garden City) co-sponsored a three-bill package to overturn sales and use tax exemptions that the legislature narrowly approved in late 2024.67 No fewer than 19 Michigan communities imposed local moratoriums on data center development even before the state-level repeal effort began.68
Construction Moratoriums: Hitting the Pause Button
Six states introduced data center construction moratoriums during the first two months of 2026, signaling a fundamental shift in how communities view large-scale compute infrastructure.69
| State | Moratorium Scope | Duration | Sponsor Party |
|---|---|---|---|
| New York | Facilities >20 MW; statewide | 3 years | Democrat70 |
| Georgia | All new construction | Through Feb 2027 | Democrat71 |
| Virginia | Certain local approvals | Through July 2028 | Democrat72 |
| Oklahoma | All new data centers | Through late 2029 | Republican73 |
| Vermont | Statewide | Under consideration | Democrat74 |
| Maryland | Regional | Under consideration | Republican75 |
New York's proposal, introduced by State Senator Liz Krueger and Assembly member Anna Kelles on February 6, 2026, drew particular attention.76 The bill (S.9144) would halt permits for new data centers exceeding 20 MW for three years while the Department of Environmental Conservation and Public Service Commission assess environmental impacts and recommend regulations.77 Food & Water Watch described the measure as "the most robust data center moratorium bill introduced nationwide."78
The bipartisan nature of these efforts underscores the depth of public frustration. Democrats sponsored bills in New York, Virginia, Georgia, and Vermont. Republicans led the charge in Maryland and Oklahoma.79 The political calculus has shifted: elected officials now view data center cost-shifting as a liability with voters, not an economic development asset.
The NDA Transparency Movement
A parallel trend targets the secrecy surrounding data center development deals. Lawmakers in five states have proposed prohibiting governments from signing nondisclosure agreements with data center developers.80 New Jersey emerged as an early mover on transparency, with bill S3379 (introduced February 9, 2026) requiring data center operators to submit semi-annual water and energy usage reports to the Board of Public Utilities.81
The NDA backlash stems from documented cases of communities approving projects without understanding their resource impacts. At least four Wisconsin communities signed secrecy agreements for billion-dollar data center projects, preventing public disclosure of energy consumption, water usage, and tax incentive terms before construction began.82
The Industry Counterargument
Not every analysis supports the narrative that data centers uniformly raise costs. Amazon commissioned consulting firm E3 (Energy + Environmental Economics) to produce "Tailored for Scale: Designing Electric Rates and Tariffs for Large Loads," released in December 2025.83 The study analyzed Amazon data centers in four utility territories (Pacific Gas & Electric, Umatilla Electric Cooperative, Dominion Energy, and Entergy) and concluded that the facilities evaluated generated surplus utility revenue rather than cost subsidies.84
E3 projected $3.4 million in surplus revenue from a hypothetical 100 MW facility in 2025, growing to $6.1 million by 2030.85 The study argued that regulators have "considerable latitude to design tariffs applicable to large loads in ways that provide revenue sufficiency, do not unduly discriminate, do not lead to excessive cost shifts, and promote broader state policy objectives."86
A separate 2026 report by Charles River Associates for the Edison Electric Institute reached similar conclusions, finding that data centers "were generally not the cause of rate increases" in areas where prices rose.87
Consumer advocates challenged both studies' methodologies. IEEFA's analysis attributed 63% of PJM's 2025-2026 price increase directly to data center load growth.88 The Citizens Utility Board and NRDC jointly warned that PJM states face up to $163 billion in additional capacity costs and potential forced blackouts if demand growth continues outpacing supply.89 Yale Climate Connections framed the disparity bluntly: "Home electricity bills are skyrocketing. For data centers, not so much."90
The disconnect between facility-level economics and system-level impact sits at the heart of the policy debate. An individual data center may generate surplus revenue for its host utility while simultaneously driving region-wide capacity costs that dwarf that surplus by orders of magnitude.
What Comes Next: The 2026-2028 Regulatory Landscape
Several critical decisions will shape data center economics over the next 24 months:
PJM Price Cap Extension. PJM agreed on February 12, 2026, to seek FERC approval for extending the capacity price cap beyond its current two-auction window.91 Without the extension, clearing prices could exceed $500/MW-day, pushing annual capacity costs above $30 billion.92 FERC's decision will directly determine whether the $100 billion or $163 billion cost scenario materializes.
Oregon PUC Rate Determination. The Oregon Public Utility Commission will set the actual rate for the new data center classification created by the POWER Act.93 PGE proposed a 25% increase with a "Peak Growth Modifier" for large-load customers.94 The PUC's decision will establish a precedent other states watch closely.
Virginia Crossover Deadline. Virginia's legislative session faces a crossover deadline on February 18 and adjournment on March 14.95 SB 253's fate, along with bills addressing tax incentive transparency and energy standards, will determine whether the nation's largest data center market enacts meaningful cost reallocation.
New York Moratorium Vote. If passed, S.9144 would create the most restrictive data center development environment in any major U.S. market, potentially redirecting billions in investment to other states.96
FERC Colocation Policy. FERC's ongoing review of data center co-location at existing power plants will determine whether behind-the-meter arrangements can reduce capacity market pressure or simply shift costs differently.97
Key Takeaways
For Infrastructure Planners
The era of cheap, no-strings-attached power for data centers has ended. Every major market in the PJM footprint now faces capacity prices at or near the FERC cap, and at least 12 states have introduced legislation creating separate rate classes, long-term contract requirements, or both. Site selection models must incorporate not only current electricity rates but projected regulatory trajectories across a 10-15 year horizon. Facilities built today in states with pending rate reform will operate under fundamentally different economics by the time they reach full capacity.
For Operations Teams
Organizations like Introl, with 550 HPC-specialized field engineers across 257 global locations, understand the operational implications of these shifts. When capacity costs rise 10x and regulators mandate separate rate classes, operational efficiency stops being an optimization exercise and becomes a survival requirement. Power usage effectiveness, demand response participation, and load management directly impact whether a facility remains economically viable under new rate structures. The 100,000-GPU deployment capability Introl maintains reflects the scale at which these cost pressures compound.
For Strategic Decision-Makers
The regulatory landscape has bifurcated. States like Texas (ERCOT market, no capacity auction) and states with nuclear co-location pathways offer different cost profiles than PJM territory. However, moratorium proposals in New York, Oklahoma, and Georgia demonstrate that even non-PJM markets face political risk. The winning strategy involves diversified geography, long-term power procurement (PPAs, behind-the-meter generation), and proactive engagement with rate design proceedings before they produce unfavorable outcomes. Waiting for the regulatory dust to settle means accepting whatever rate structures emerge from processes driven by consumer advocates and ratepayer frustration.
The electricity pricing landscape for data centers continues to evolve rapidly. Introl tracks these developments as part of our broader infrastructure intelligence coverage. For operational support across 257 locations, visit introl.com/coverage-area.
-
PJM Interconnection, "2026/2027 Base Residual Auction Report," July 22, 2025. PJM BRA Report ↩
-
PJM Interconnection, "2024/2025 RPM Base Residual Auction Results." PJM BRA Report ↩
-
IEEFA, "Projected data center growth spurs PJM capacity prices by factor of 10." IEEFA Analysis ↩
-
Synapse Energy Economics, "Risks of Rapid Data Center Growth in PJM." Synapse Energy ↩
-
NRDC, "Rising Demand from Data Centers Driving Reliability, Cost Concerns," October 2025. NRDC Press Release ↩
-
NRDC, "Building Data Centers Without Breaking PJM." NRDC Analysis ↩
-
PJM Interconnection, "About PJM." PJM Inside Lines ↩
-
PJM Interconnection, "2027/2028 Base Residual Auction Report," December 17, 2025. PJM BRA Report ↩
-
IEEFA, "Projected data center growth spurs PJM capacity prices by factor of 10." IEEFA Analysis ↩
-
Utility Dive, "PJM capacity prices set another record with 22% jump." Utility Dive ↩
-
Utility Dive, "Data centers were 40% of PJM capacity costs in last auction: market monitor." Utility Dive ↩
-
PJM Interconnection, "PJM Auction Procures 134,479 MW of Generation Resources," December 17, 2025. PJM News Release ↩
-
Utility Dive, "PJM capacity prices hit record high as grid operator falls short of reliability target." Utility Dive ↩
-
State of Delaware News, "DPA Calls for Extension of PJM Capacity Price Cap to Protect Consumers," February 13, 2026. Delaware News ↩
-
Power Magazine, "PJM, Facing Capacity Shortage, Agrees to Lower Auction Price Cap." Power Magazine ↩
-
Canary Media, "PJM's capacity costs hit record as grid falls short on supply." Canary Media ↩
-
IEEFA, "Projected data center growth spurs PJM capacity prices by factor of 10." IEEFA Analysis ↩
-
Utility Dive, "Data centers were 40% of PJM capacity costs in last auction: market monitor." Utility Dive ↩
-
Virginia Mercury, "Bill would put more energy costs on data centers, slash residential customers' rates," February 10, 2026. Virginia Mercury ↩
-
NRDC, "PJM Board to Decide on Higher Bills for 67 Million Americans Due to Data Centers." NRDC ↩
-
NRDC, "PJM Board to Decide on Higher Bills for 67 Million Americans Due to Data Centers." NRDC ↩
-
E&E News by POLITICO, "Data center boom sparks sticker shock for PJM ratepayers." E&E News ↩
-
Citizens Utility Board and NRDC, "Data center distress: CUB, NRDC experts warn PJM states could get hit with forced blackouts, $163B in electricity capacity costs," October 23, 2025. CUB ↩
-
Synapse Energy Economics, "Tackling the PJM Electricity Cost Crisis." Synapse Energy ↩
-
GridShopper, "PJM Capacity Costs Drive Major Utility Rate Increases." GridShopper ↩
-
State of Delaware News, "DPA Calls for Extension of PJM Capacity Price Cap to Protect Consumers," February 13, 2026. Delaware News ↩
-
Diversegy, "FERC Approves PJM Capacity Cap & Collar for 2026-2028." Diversegy ↩
-
PJM Interconnection, 2025 Long-Term Load Forecast. Cited in IEEFA analysis. IEEFA ↩
-
PJM Interconnection, 2025 Long-Term Load Forecast. Cited in IEEFA analysis. IEEFA ↩
-
Utility Dive, "Solving PJM's data center problem." Utility Dive ↩
-
Utility Dive, "Solving PJM's data center problem." Utility Dive ↩
-
PJM Interconnection, "2027/2028 Base Residual Auction Report," December 17, 2025. PJM BRA Report ↩
-
PJM Interconnection, "2027/2028 Base Residual Auction Report," December 17, 2025. PJM BRA Report ↩
-
PJM Interconnection, "PJM Auction Procures 134,479 MW of Generation Resources," December 17, 2025. PJM Inside Lines ↩
-
Utility Dive, "PJM capacity prices hit record high as grid operator falls short of reliability target." Utility Dive ↩
-
MultiState, "Here's What You Need To Know About Data Center Policy Trends," November 4, 2025. MultiState ↩
-
OPB, "Oregon Legislature passes 'POWER Act,' targeting industrial energy users like data centers," June 5, 2025. OPB ↩
-
Clean Energy Transition, "Oregon's POWER Act Addresses Ratepayer Impact of Large Energy Users." Clean Energy Transition ↩
-
Oregon CUB, "POWER Act Passes Oregon House." Oregon CUB ↩
-
MIRATECH, "Data Centers to Pay New Electricity Rate under Oregon Bill that has Passed." MIRATECH ↩
-
Oregon CUB, "Protecting Oregonians With Energy Responsibility (POWER) Act (HB 3546)." Oregon CUB ↩
-
OPB, "'POWER Act' bill would require Oregon's large energy users like data centers pay fair share of energy use," March 6, 2025. OPB ↩
-
OPB, "As electricity costs rise, everyone wants data centers to pick up their tab. But how?" February 13, 2026. OPB ↩
-
Oregon CUB, "Oregonians Speak Up for the POWER Act (HB 3546)." Oregon CUB ↩
-
Virginia Mercury, "Bill would put more energy costs on data centers, slash residential customers' rates," February 10, 2026. Virginia Mercury ↩
-
Virginia Mercury, "Bill would put more energy costs on data centers, slash residential customers' rates," February 10, 2026. Virginia Mercury ↩
-
Duane Morris LLP, "Data Centers - Virginia Bill SB 253 Directed at Large Electricity Users," February 11, 2026. Duane Morris Blog ↩
-
Stateline, "With electricity bills rising, some states consider new data center laws," February 5, 2026. Stateline ↩
-
OK Energy Today, "Boles Files Bill Protects Ratepayers From Data Center Costs," January 2026. OK Energy Today ↩
-
Inside Climate News, "Virginia Regulators Approve New Dominion Rates, Assign More Costs to Data Centers," January 7, 2026. Inside Climate News ↩
-
MultiState, "States Rethink Data Center Tax Incentives as Costs Soar," February 4, 2026. MultiState ↩
-
Cardinal News, "Tax abatement for data centers is now $1.6 billion a year. Is that a giveaway or a bargain?" January 22, 2026. Cardinal News ↩
-
Georgia Public Broadcasting, "Resistance to data centers fuels flood of Georgia bills targeting the industry," January 28, 2026. GPB ↩
-
Inside Climate News, "Michigan Lawmakers Introduce Bill to Repeal Data Center Tax Incentives," December 16, 2025. Inside Climate News ↩
-
Bloomberg Tax, "State Tax Breaks for Data Centers Come Under Fire With AI Boom." Bloomberg Tax ↩
-
Bloomberg Tax, "Data Centers Won Billions in Tax Breaks. Some States Are Balking." Bloomberg Tax ↩
-
Cardinal News, "Tax abatement for data centers is now $1.6 billion a year. Is that a giveaway or a bargain?" January 22, 2026. Cardinal News ↩
-
Georgia Department of Audits and Accounts, "Tax Incentive Evaluation: Georgia High-Tech Data Center Equipment Exemption." Georgia Audits ↩
-
Bridge Michigan, "$90M data center tax break plan headed to Gov. Whitmer after final passage." Bridge Michigan ↩
-
MultiState, "States Rethink Data Center Tax Incentives as Costs Soar," February 4, 2026. MultiState ↩
-
Good Jobs First, "Virginia Tax Revenue Losses to Data Centers Soar to $1.6 Billion for FY25." Good Jobs First ↩
-
The Register, "Virginia's datacenter tax breaks cost state $1.6B in 2025," January 7, 2026. The Register ↩
-
VPM, "Virginia lawmakers propose a bevy of data center reform bills," January 16, 2026. VPM ↩
-
Georgia Department of Revenue, "Data Centers Sales & Use Tax Exemption - Aggregate Expenditures by County." Georgia DOR ↩
-
Data Center Dynamics, "Georgia Senate passes bill to suspend data center tax exemptions." DCD ↩
-
Georgia Public Broadcasting, "Resistance to data centers fuels flood of Georgia bills targeting the industry," January 28, 2026. GPB ↩
-
Bridge Michigan, "Michigan lawmakers unveil plan to repeal data center tax breaks." Bridge Michigan ↩
-
Bridge Michigan, "Data center moratoriums pile up in Michigan. No one knows if they'll work." Bridge Michigan ↩
-
The Deep Dive, "Six States Introduce Data Center Moratorium Bills as AI Boom Strains Power Grids." The Deep Dive ↩
-
TechCrunch, "New York lawmakers propose a 3-year pause on new data centers," February 7, 2026. TechCrunch ↩
-
Georgia Public Broadcasting, "Resistance to data centers fuels flood of Georgia bills targeting the industry," January 28, 2026. GPB ↩
-
Stateline, "With electricity bills rising, some states consider new data center laws," February 5, 2026. Stateline ↩
-
Stateline, "With electricity bills rising, some states consider new data center laws," February 5, 2026. Stateline ↩
-
The Deep Dive, "Six States Introduce Data Center Moratorium Bills as AI Boom Strains Power Grids." The Deep Dive ↩
-
The Deep Dive, "Six States Introduce Data Center Moratorium Bills as AI Boom Strains Power Grids." The Deep Dive ↩
-
New York State Legislature, Bill S.9144. Cited in TechCrunch, "New York lawmakers propose a 3-year pause on new data centers," February 7, 2026. TechCrunch ↩
-
The Real Deal, "New York lawmakers introduce data center development moratorium," February 10, 2026. The Real Deal ↩
-
Common Dreams, "'Strongest-in-the-Nation' Data Center Moratorium Proposed in NY." Common Dreams ↩
-
The Deep Dive, "Six States Introduce Data Center Moratorium Bills as AI Boom Strains Power Grids." The Deep Dive ↩
-
Boondoggle, "Four Ways States Are Taking on the Data Center Machine." Boondoggle ↩
-
New Jersey Legislature, Bill S3379, introduced February 9, 2026. LegiScan ↩
-
Wisconsin Watch, "At least four Wisconsin communities signed secrecy deals for billion-dollar data centers," January 2026. Wisconsin Watch ↩
-
E3, "Tailored for Scale: Designing Electric Rates and Tariffs for Large Loads," December 2025. E3 Study ↩
-
E3, "Tailored for Scale: Designing Electric Rates and Tariffs for Large Loads," December 2025. E3 PDF ↩
-
E3, "Tailored for Scale: Designing Electric Rates and Tariffs for Large Loads," December 2025. E3 Study ↩
-
E3, "Tailored for Scale: Designing Electric Rates and Tariffs for Large Loads," December 2025. E3 PDF ↩
-
CNN Business, "Here's how AI data centers affect the electrical grid," January 18, 2026. CNN ↩
-
IEEFA, "Projected data center growth spurs PJM capacity prices by factor of 10." IEEFA ↩
-
Citizens Utility Board and NRDC, "Data center distress," October 23, 2025. CUB ↩
-
Yale Climate Connections, "Home electricity bills are skyrocketing. For data centers, not so much," January 2026. Yale Climate Connections ↩
-
Diversegy, "FERC Approves PJM Capacity Cap & Collar for 2026-2028." Diversegy ↩
-
Power Magazine, "PJM, Facing Capacity Shortage, Agrees to Lower Auction Price Cap." Power Magazine ↩
-
OPB, "As electricity costs rise, everyone wants data centers to pick up their tab. But how?" February 13, 2026. OPB ↩
-
OPB, "'POWER Act' bill would require Oregon's large energy users like data centers pay fair share of energy use," March 6, 2025. OPB ↩
-
Cardinal News, "Tax abatement for data centers is now $1.6 billion a year. Is that a giveaway or a bargain?" January 22, 2026. Cardinal News ↩
-
TechCrunch, "New York lawmakers propose a 3-year pause on new data centers," February 7, 2026. TechCrunch ↩
-
American Action Forum, "Emergency Energy Auction to Prevent Data Center-driven Rate Increases." AAF ↩