Data Centers as Grid Stabilizers: How AI Infrastructure Became a Power Asset

NVIDIA, EPRI, and Oracle demonstrate 25% power reduction during peak demand. New reference design could unlock 100 GW of grid capacity nationwide.

Data Centers as Grid Stabilizers: How AI Infrastructure Became a Power Asset

Data Centers as Grid Stabilizers: How AI Infrastructure Became a Power Asset

A coalition of NVIDIA, Oracle, Salt River Project, and the Electric Power Research Institute demonstrated a 25% power reduction sustained over three hours during a Phoenix grid stress event—without compromising AI workload performance. The results, published in Nature Energy, mark the first peer-reviewed validation of data center demand flexibility at commercial scale.1

TL;DR

Software-based workload orchestration enabled 256 NVIDIA GPUs to reduce power consumption by 25% during peak grid demand on May 3, 2025, in Phoenix, Arizona. The demonstration proves data centers can function as "flexible resources" that respond to utility signals in real time. A new reference design based on these results could unlock 100 GW of existing U.S. grid capacity—equivalent to 20% of total national electricity consumption—without requiring new transmission or generation infrastructure.2 The 96-MW Aurora AI Factory in Virginia, opening in H1 2026, will serve as the first facility built to this standard.3


The Problem Data Centers Created

Northern Virginia hosts the world's largest concentration of data centers, consuming approximately 26% of statewide electricity demand compared to the 4% U.S. average.4 On July 10, 2024, this concentration nearly caused a regional blackout.

A lightning arrestor failed on a 230 kV transmission line at 7 p.m. EST. The resulting voltage fluctuation triggered an automated safety response: 60 data centers simultaneously disconnected from the grid and switched to backup generators.5 This created a sudden 1,500 MW load swing that sent grid operator PJM and utility Dominion Energy scrambling to cut generation fast enough to prevent infrastructure damage and regionwide blackouts.6

The incident exposed a fundamental vulnerability. Data centers have traditionally operated as inflexible loads—demanding 100% maximum electricity draw 24/7/365 regardless of grid conditions.7 This rigidity drives the need for massive infrastructure upgrades that take years to permit and build.

Metric Current State Impact
Virginia data center contracted power 40 GW (as of Dec 2024) 88% increase since July 20248
Northern Virginia demand vs. capacity Approaching collapse Line voltage collapse possible by 20299
PJM reliability shortfall 6 GW by 2027 Largest projected strain in history10
Virginia power demand growth 183% by 2040 Equivalent to 11.7M homes11

The North American Electric Reliability Corporation created a task force specifically to study this vulnerability following the July 2024 incident.12 Texas alone has experienced 30 similar incidents since 2020 caused by data centers suddenly dropping off the grid.13


The Phoenix Demonstration: Proof of Concept

Emerald AI, an NVIDIA-backed startup, designed a software platform called Emerald Conductor that orchestrates AI workloads in response to grid signals. The Phoenix demonstration through EPRI's DCFlex program tested whether this approach could work under real-world conditions.14

Test Parameters

Date: May 3, 2025—a hot day in Phoenix with high air-conditioning demand15

Infrastructure: 256 NVIDIA GPUs in an Oracle commercial data center16

Grid conditions: Salt River Project experienced peak demand at 6 p.m.17

Target: Sustained 25% power reduction during grid stress event18

Results

The data center reduced consumption through a 15-minute ramp down, maintained the 25% power reduction over three hours, then ramped back up without exceeding its original baseline consumption.19

"This test was an opportunity to completely reimagine AI data centers as helpful resources to help us operate the power grid more effectively and reliably," said David Rousseau, president of Salt River Project.20

Workload Flexibility Tiers

The demonstration categorized computing workloads into priority tiers:

Tier Description Flexibility
Flex 1 Critical jobs No ability to slow or delay processing
Flex 2 Moderate priority Some flexibility to delay or adjust processing
Flex 3 Background workloads Full flexibility to shift processing times21

The orchestration software shifted Flex 3 workloads and throttled Flex 2 workloads while protecting Flex 1 operations. AI training jobs proved particularly amenable to scheduling flexibility since completing a training run hours later has minimal business impact compared to real-time inference.22


The Technology Stack

Emerald AI Platform

Emerald Conductor integrates with NVIDIA's AI software stack through several key components:

  • GridLink: Receives real-time signals from utilities about grid conditions23
  • NVIDIA Mission Control: Coordinates with NVIDIA AI Enterprise components including NIM microservices24
  • Workload orchestrator: Manages job prioritization and power allocation across GPU clusters25

This architecture provides the crucial link between the grid's real-time needs and the data center's operational controls, enabling intelligent workload scheduling and power management.26

Alternative Approaches

Verrus (Alphabet spinoff):

Verrus, spun out from Alphabet's Sidewalk Infrastructure Partners, takes a different approach: battery-backed flexibility. The company demonstrated its technology at NREL's 70-MW facility in Colorado.27

Capability Specification
Response time Within 10 seconds of utility request28
Load curtailment Up to 100% within 1 minute29
Battery runtime Approximately 4 hours on pure battery30
Backup power BESS replaces diesel generators31

"Verrus' technology has the potential to impact how data centers—when intentionally designed for flexibility—can provide meaningful value to grid operators," said Ty Ferretti, Partnership Development Lead at NREL.32

First Verrus facilities are expected in Arizona, California, and Massachusetts, operational by 2026 or 2027.33


The Aurora AI Factory: Reference Implementation

On October 29, 2025, NVIDIA, Emerald AI, EPRI, Digital Realty, and PJM announced the world's first power-flexible AI Factory.34 The 96-MW Aurora AI Factory in Manassas, Virginia, will serve as both the reference implementation and a certification standard for power-flexible AI infrastructure.35

Facility Details

Specification Value
Capacity 96 MW
Location Manassas, Virginia
Developer Digital Realty
Grid operator PJM Interconnection
Opening H1 202636

Testing Protocol

The Aurora facility will undergo demonstration testing through EPRI's DCFlex Initiative. Testing will simulate:

  • Demand spikes during summer heatwaves
  • Sudden drops in renewable energy generation
  • Real-time responses to grid stress events37

"As the world's demand for AI compute grows, infrastructure innovation must evolve with it. Digital Realty is committed to advancing solutions that integrate compute performance, sustainability, and grid resiliency," said Chris Sharp, CTO of Digital Realty.38

Projected National Impact

The power-flexible reference design, if adopted nationwide, could unlock an estimated 100 GW of capacity on the existing electricity system—equivalent to 20% of total U.S. electricity consumption.39

For context: EPRI studies show data centers could consume 9% of U.S. electricity generation by 2030, more than double current consumption.40 Unlocking 100 GW of flexible capacity would meet projected AI growth for the next decade without requiring extensive new generation or transmission infrastructure.41


Why Skeptics Were Wrong

Traditional arguments against data center flexibility centered on reliability requirements. Hyperscalers promise "five nines" (99.999% uptime) in service-level agreements, leaving little room for power adjustments.42

The Flexibility Math

Analysis from the Energy Institute at Haas revealed a critical insight: grid strain concentrates in a very small number of hours per year. In the vast majority of hours, spare capacity exists to serve new data center loads.43

Curtailment Tolerance Unlocked Capacity
0.25% of annual hours (~22 hours) 76 GW
1% of annual hours (~88 hours) 126 GW44

A steel mill or AI data center that tolerates less than 100 hours of curtailment per year could allow utilities to provide many gigawatts of new capacity without proportionate transmission or generation expansion.45

Workload Realities

The Phoenix demonstration proved that AI workloads contain inherent flexibility that traditional analysis overlooked:

  • Training workloads: Not time-sensitive; completing a run hours later has minimal business impact46
  • Inference workloads: Some require real-time response, but many batch inference jobs can shift47
  • Checkpointing: Brief dips in power during synchronized checkpoints already occur naturally48

"Certain inference workloads in particular may not have flexibility, but training a model is certainly not as time sensitive," noted researchers studying the Phoenix results.49


EPRI DCFlex Initiative: Scaling the Model

EPRI launched the DCFlex initiative in 2024 as a three-year effort to advance understanding of data center demand flexibility and test improvements under real-world conditions.50

Participation

The initiative brings together:

  • More than 60 utilities, researchers, hyperscalers, and tech innovators51
  • Hyperscalers including Google, Meta, Oracle, and Microsoft52
  • Technology companies including NVIDIA53
  • Grid operators and equipment suppliers54

Active Demonstrations

Location Partners Focus
Phoenix, Arizona Oracle, NVIDIA, Emerald AI, SRP Computational flexibility during peak demand55
Lenoir, North Carolina Google, Duke Energy Workload orchestration for grid support56
Charlotte, North Carolina Multiple partners Demand response validation
Paris, France European partners Power quality response testing57

More demonstrations are anticipated throughout 2026.58


Implementation Requirements

For Data Center Operators

Adopting power-flexible operations requires several infrastructure and operational changes:

Software integration:

  • Real-time grid signal receivers
  • Workload orchestration platforms
  • AI-aware scheduling systems59

Operational changes:

  • Workload classification by flexibility tier
  • SLA modifications to accommodate brief curtailments
  • Customer communication about flexibility programs60

No hardware retrofits required: The Phoenix demonstration proved software-only orchestration can achieve meaningful flexibility without energy storage systems or hardware modifications.61

For Utilities

Utilities seeking to integrate data center flexibility must develop:

  • Real-time signaling infrastructure to communicate grid conditions
  • Tariff structures that incentivize flexible behavior
  • Verification and measurement protocols for demand response62

"Data centers are not charities, and they will require incentives to maximize flexibility," noted researchers from Resources for the Future.63


The Grid Investment Reality

Goldman Sachs Research estimates $720 billion of grid spending through 2030 may be needed to accommodate data center growth.64 Transmission projects can take several years to permit and several more to build, creating potential bottlenecks for data center expansion.65

Power-flexible data centers offer an alternative path. Rather than waiting for new generation and transmission capacity, operators can tap existing spare capacity during non-peak hours while curtailing during the limited stress periods.

Approach Timeline Cost Capacity Added
New transmission 5-10 years High Proportional to investment
New generation 3-7 years High Proportional to investment
Flexible load integration 1-2 years Low 76-126 GW with modest curtailment66

The technology needed for data centers to function as flexible grid assets could be available in the next 1-2 years. The DCFlex Initiative aims to deploy five to ten large-scale flexibility hubs by 2027 that demonstrate how data centers can provide demand flexibility and grid services.67


Introl Perspective

Deploying power-flexible AI infrastructure requires expertise that extends beyond traditional data center construction. The integration of workload orchestration software, real-time grid communication systems, and GPU cluster management demands specialized knowledge across multiple domains.

Introl's coverage area includes 257 locations worldwide with 550 field engineers specializing in high-performance computing and AI infrastructure. This geographic reach and technical depth positions infrastructure partners to support the deployment of flexible AI facilities as the reference design scales from Aurora to national adoption.


Key Takeaways

For Infrastructure Planners

  • Power-flexible designs unlock existing grid capacity without waiting for new transmission
  • The Aurora reference implementation provides a certification pathway for new facilities
  • Software-based flexibility requires no hardware retrofits in existing clusters

For Operations Teams

  • Workload classification into flexibility tiers enables intelligent curtailment
  • AI training workloads offer significant scheduling flexibility without SLA violations
  • Real-time grid signal integration adds operational complexity but unlocks capacity

For Strategic Planners

  • 100 GW of potential capacity sits dormant on the existing U.S. grid
  • First-mover adoption of flexibility standards may accelerate interconnection timelines
  • Utility partnerships increasingly require demonstrated demand response capability

References


  1. TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html 

  2. Emerald AI. "Emerald AI Teams with NVIDIA and Partners to Develop Power-Flexible AI Factory." PR Newswire, October 29, 2025. https://www.prnewswire.com/news-releases/emerald-ai-teams-with-nvidia-and-partners-to-develop-power-flexible-ai-factory-and-reference-design-to-unlock-100-gw-of-grid-capacity-and-supercharge-the-ai-revolution-302597760.html 

  3. Data Center Dynamics. "Nvidia to deploy Emerald AI's orchestration software at 96MW Aurora data center in Manassas, Virginia." https://www.datacenterdynamics.com/en/news/nvidia-to-deploy-emerald-ais-orchestration-software-at-96mw-aurora-data-center-in-manassas-virginia/ 

  4. Power Magazine. "Data Centers, the Grid, and the Assumptions That Don't Hold Up." https://www.powermag.com/data-centers-the-grid-and-the-assumptions-that-dont-hold-up/ 

  5. Data Center Dynamics. "Virginia narrowly avoided power cuts when 60 data centers dropped off the grid at once." https://www.datacenterdynamics.com/en/news/virginia-narrowly-avoided-power-cuts-when-60-data-centers-dropped-off-the-grid-at-once/ 

  6. GridStatus Blog. "Byte Blackouts: How large data center loads are surfacing new issues." https://blog.gridstatus.io/byte-blackouts-large-data-center-loads-new-issues-pjm/ 

  7. Rocky Mountain Institute. "Fast, Flexible Solutions for Data Centers." https://rmi.org/fast-flexible-solutions-for-data-centers/ 

  8. Cardinal News. "Energy demand will outstrip supply in Virginia as data centers proliferate." April 11, 2025. https://cardinalnews.org/2025/04/11/energy-demand-will-outstrip-supply-in-virginia-as-data-centers-proliferate/ 

  9. Prince William Times. "Data centers expected to spike residential utility bills." https://www.princewilliamtimes.com/news/data-centers-expected-to-spike-electricity-costs/ 

  10. Utility Dive. "Energy evolution: Meeting the demands of an AI-powered world." https://www.utilitydive.com/news/ai-grid-data-center-epri/807800/ 

  11. JLARC Virginia. "Data Centers in Virginia." 2024. https://jlarc.virginia.gov/landing-2024-data-centers-in-virginia.asp 

  12. Bisnow. "Near Misses Instill Fears Over Widespread Data Center-Induced Blackouts." https://www.bisnow.com/national/news/data-center/data-centers-nearly-caused-virginia-blackout-according-to-report-128565 

  13. Data Center Dynamics. "Virginia narrowly avoided power cuts when 60 data centers dropped off the grid at once." https://www.datacenterdynamics.com/en/news/virginia-narrowly-avoided-power-cuts-when-60-data-centers-dropped-off-the-grid-at-once/ 

  14. Power Magazine. "Data Centers Can Be a Flexible Power Load—Here's Why That Matters." https://www.powermag.com/blog/data-centers-can-be-a-flexible-power-load-heres-why-that-matters/ 

  15. TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html 

  16. NVIDIA Blog. "How AI Factories Can Help Relieve Grid Stress." https://blogs.nvidia.com/blog/ai-factories-flexible-power-use/ 

  17. TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html 

  18. EPRI DCFlex Program. https://dcflex.sf.epri.com/ 

  19. TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html 

  20. TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html 

  21. Power Magazine. "Data Centers Can Be a Flexible Power Load—Here's Why That Matters." https://www.powermag.com/blog/data-centers-can-be-a-flexible-power-load-heres-why-that-matters/ 

  22. Energy Institute Blog. "Can Data Centers Flex Their Power Demand?" April 14, 2025. https://energyathaas.wordpress.com/2025/04/14/can-data-centers-flex-their-power-demand/ 

  23. Emerald AI. "Emerald AI Teams with NVIDIA and Partners." https://www.emeraldai.co/blog/launching-the-first-power-flexible-ai-factory-with-nvidia 

  24. NVIDIA Resources. "Emerald AI Orchestrates AI Factories to Help Relieve Grid Stress." https://resources.nvidia.com/en-us-energy-utilities/ai-factories-flexible 

  25. Latitude Media. "How the world's first flexible AI factory will work in tandem with the grid." https://www.latitudemedia.com/news/how-the-worlds-first-flexible-ai-factory-will-work-in-tandem-with-the-grid/ 

  26. Emerald AI. "Emerald AI Teams with NVIDIA and Partners." PR Newswire. https://www.prnewswire.com/news-releases/emerald-ai-teams-with-nvidia-and-partners-to-develop-power-flexible-ai-factory-and-reference-design-to-unlock-100-gw-of-grid-capacity-and-supercharge-the-ai-revolution-302597760.html 

  27. Latitude Media. "Verrus successfully demos its flexible data center technology." https://www.latitudemedia.com/news/verrus-successfully-demos-its-flexible-data-center-technology/ 

  28. Verrus. "Verrus Demonstrates Industry Leading Grid-Interactive Data Center Technology at Scale, in Collaboration with NREL." https://verrusdata.com/news/verrus-nrel 

  29. Volts. "Can data centers be good grid citizens?" https://www.volts.wtf/p/can-data-centers-be-good-grid-citizens 

  30. Latitude Media. "The data center of the future looks like a massive virtual power plant." https://www.latitudemedia.com/news/the-data-center-of-the-future-looks-like-a-massive-virtual-power-plant/ 

  31. TechCrunch. "Alphabet spin-off SIP launches Verrus, a data center concept built around battery 'microgrids'." March 11, 2024. https://techcrunch.com/2024/03/11/sip-verrus-data-center/ 

  32. Verrus. "Verrus Demonstrates Industry Leading Grid-Interactive Data Center Technology at Scale, in Collaboration with NREL." https://verrusdata.com/news/verrus-nrel 

  33. Latitude Media. "A status update on data center flexibility." https://www.latitudemedia.com/news/a-status-update-on-data-center-flexibility/ 

  34. American Public Power Association. "NVIDIA, Emerald AI, EPRI, PJM and Others to Develop Power-Flexible AI Factory." https://www.publicpower.org/periodical/article/nvidia-emerald-ai-epri-pjm-and-others-develop-power-flexible-ai-factory 

  35. Emerald AI. "Emerald AI Teams with NVIDIA and Partners." https://www.emeraldai.co/blog/launching-the-first-power-flexible-ai-factory-with-nvidia 

  36. Data Center Dynamics. "Nvidia to deploy Emerald AI's orchestration software at 96MW Aurora data center in Manassas, Virginia." https://www.datacenterdynamics.com/en/news/nvidia-to-deploy-emerald-ais-orchestration-software-at-96mw-aurora-data-center-in-manassas-virginia/ 

  37. Latitude Media. "How the world's first flexible AI factory will work in tandem with the grid." https://www.latitudemedia.com/news/how-the-worlds-first-flexible-ai-factory-will-work-in-tandem-with-the-grid/ 

  38. Emerald AI. "Emerald AI Teams with NVIDIA and Partners." PR Newswire. https://www.prnewswire.com/news-releases/emerald-ai-teams-with-nvidia-and-partners-to-develop-power-flexible-ai-factory-and-reference-design-to-unlock-100-gw-of-grid-capacity-and-supercharge-the-ai-revolution-302597760.html 

  39. Yahoo Finance. "Emerald AI Teams with NVIDIA and Partners to Develop Power-Flexible AI Factory." https://finance.yahoo.com/news/emerald-ai-teams-nvidia-partners-093000156.html 

  40. EPRI. "Data Center Flexible Load Initiative." https://www.epri.com/about/media-resources/press-release/yimzJV2Xnv9cqiZTaU1zxBeDlEtwYQk1 

  41. Utility Dive. "EPRI launches data center flexibility initiative with utilities, Google, Meta, NVIDIA." https://www.utilitydive.com/news/epri-launches-data-center-flexibility-initiative-with-NVIDIA-google-meta/731490/ 

  42. Energy Institute Blog. "Can Data Centers Flex Their Power Demand?" April 14, 2025. https://energyathaas.wordpress.com/2025/04/14/can-data-centers-flex-their-power-demand/ 

  43. Energy Institute Blog. "Can Data Centers Flex Their Power Demand?" April 14, 2025. https://energyathaas.wordpress.com/2025/04/14/can-data-centers-flex-their-power-demand/ 

  44. Rocky Mountain Institute. "Fast, Flexible Solutions for Data Centers." https://rmi.org/fast-flexible-solutions-for-data-centers/ 

  45. Resources for the Future. "The Hype on Hyperscalers: Data Centers and Growing Electricity Demand." https://www.resources.org/common-resources/the-hype-on-hyperscalers-data-centers-and-growing-electricity-demand/ 

  46. Energy Institute Blog. "Can Data Centers Flex Their Power Demand?" April 14, 2025. https://energyathaas.wordpress.com/2025/04/14/can-data-centers-flex-their-power-demand/ 

  47. Latitude Media. "The mechanics of data center flexibility." https://www.latitudemedia.com/news/catalyst-the-mechanics-of-data-center-flexibility/ 

  48. Energeia USA. "The Future of Data Center Electrical Grid Impacts." https://energeia-usa.com/data-center-grid-impacts/ 

  49. Energy Institute Blog. "Can Data Centers Flex Their Power Demand?" April 14, 2025. https://energyathaas.wordpress.com/2025/04/14/can-data-centers-flex-their-power-demand/ 

  50. EPRI. "DCFlex: Data Center Flexible Load Initiative." https://www.epri.com/research/products/000000003002031004 

  51. Utility Dive. "Energy evolution: Meeting the demands of an AI-powered world." https://www.utilitydive.com/news/ai-grid-data-center-epri/807800/ 

  52. Utility Dive. "EPRI launches data center flexibility initiative with utilities, Google, Meta, NVIDIA." https://www.utilitydive.com/news/epri-launches-data-center-flexibility-initiative-with-NVIDIA-google-meta/731490/ 

  53. EPRI DCFlex. https://dcflex.sf.epri.com/ 

  54. EPRI Journal. "Flexible Loads, Resilient Grids." https://eprijournal.com/flexible-loads-resilient-grids/ 

  55. Power Magazine. "Data Centers Can Be a Flexible Power Load—Here's Why That Matters." https://www.powermag.com/blog/data-centers-can-be-a-flexible-power-load-heres-why-that-matters/ 

  56. EPRI Journal. "Flexible Loads, Resilient Grids." https://eprijournal.com/flexible-loads-resilient-grids/ 

  57. EPRI Journal. "Flexible Loads, Resilient Grids." https://eprijournal.com/flexible-loads-resilient-grids/ 

  58. Utility Dive. "Energy evolution: Meeting the demands of an AI-powered world." https://www.utilitydive.com/news/ai-grid-data-center-epri/807800/ 

  59. NVIDIA Blog. "How AI Factories Can Help Relieve Grid Stress." https://blogs.nvidia.com/blog/ai-factories-flexible-power-use/ 

  60. Utility Dive. "Mainstreaming AI data center flexibility." https://www.utilitydive.com/news/mainstreaming-ai-data-center-flexibility/804103/ 

  61. TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html 

  62. Renewable Energy World. "As AI and data center power demand skyrockets, flexible load integration becomes a critical strategy for utilities." https://www.renewableenergyworld.com/power-grid/grid-modernization/as-ai-and-data-center-power-demand-skyrockets-flexible-load-integration-becomes-a-critical-strategy-for-utilities/ 

  63. Resources for the Future. "The Hype on Hyperscalers: Data Centers and Growing Electricity Demand." https://www.resources.org/common-resources/the-hype-on-hyperscalers-data-centers-and-growing-electricity-demand/ 

  64. Goldman Sachs. "AI to drive 165% increase in data center power demand by 2030." https://www.goldmansachs.com/insights/articles/ai-to-drive-165-increase-in-data-center-power-demand-by-2030 

  65. Goldman Sachs. "AI to drive 165% increase in data center power demand by 2030." https://www.goldmansachs.com/insights/articles/ai-to-drive-165-increase-in-data-center-power-demand-by-2030 

  66. Rocky Mountain Institute. "Fast, Flexible Solutions for Data Centers." https://rmi.org/fast-flexible-solutions-for-data-centers/ 

  67. Data Center Knowledge. "2026 Predictions: AI Sparks Data Center Power Revolution." https://www.datacenterknowledge.com/operations-and-management/2026-predictions-ai-sparks-data-center-power-revolution 

Request a Quote_

Tell us about your project and we'll respond within 72 hours.

> TRANSMISSION_COMPLETE

Request Received_

Thank you for your inquiry. Our team will review your request and respond within 72 hours.

QUEUED FOR PROCESSING