Data Centers as Grid Stabilizers: How AI Infrastructure Became a Power Asset
A coalition of NVIDIA, Oracle, Salt River Project, and the Electric Power Research Institute demonstrated a 25% power reduction sustained over three hours during a Phoenix grid stress event—without compromising AI workload performance. The results, published in Nature Energy, mark the first peer-reviewed validation of data center demand flexibility at commercial scale.1
TL;DR
Software-based workload orchestration enabled 256 NVIDIA GPUs to reduce power consumption by 25% during peak grid demand on May 3, 2025, in Phoenix, Arizona. The demonstration proves data centers can function as "flexible resources" that respond to utility signals in real time. A new reference design based on these results could unlock 100 GW of existing U.S. grid capacity—equivalent to 20% of total national electricity consumption—without requiring new transmission or generation infrastructure.2 The 96-MW Aurora AI Factory in Virginia, opening in H1 2026, will serve as the first facility built to this standard.3
The Problem Data Centers Created
Northern Virginia hosts the world's largest concentration of data centers, consuming approximately 26% of statewide electricity demand compared to the 4% U.S. average.4 On July 10, 2024, this concentration nearly caused a regional blackout.
A lightning arrestor failed on a 230 kV transmission line at 7 p.m. EST. The resulting voltage fluctuation triggered an automated safety response: 60 data centers simultaneously disconnected from the grid and switched to backup generators.5 This created a sudden 1,500 MW load swing that sent grid operator PJM and utility Dominion Energy scrambling to cut generation fast enough to prevent infrastructure damage and regionwide blackouts.6
The incident exposed a fundamental vulnerability. Data centers have traditionally operated as inflexible loads—demanding 100% maximum electricity draw 24/7/365 regardless of grid conditions.7 This rigidity drives the need for massive infrastructure upgrades that take years to permit and build.
| Metric | Current State | Impact |
|---|---|---|
| Virginia data center contracted power | 40 GW (as of Dec 2024) | 88% increase since July 20248 |
| Northern Virginia demand vs. capacity | Approaching collapse | Line voltage collapse possible by 20299 |
| PJM reliability shortfall | 6 GW by 2027 | Largest projected strain in history10 |
| Virginia power demand growth | 183% by 2040 | Equivalent to 11.7M homes11 |
The North American Electric Reliability Corporation created a task force specifically to study this vulnerability following the July 2024 incident.12 Texas alone has experienced 30 similar incidents since 2020 caused by data centers suddenly dropping off the grid.13
The Phoenix Demonstration: Proof of Concept
Emerald AI, an NVIDIA-backed startup, designed a software platform called Emerald Conductor that orchestrates AI workloads in response to grid signals. The Phoenix demonstration through EPRI's DCFlex program tested whether this approach could work under real-world conditions.14
Test Parameters
Date: May 3, 2025—a hot day in Phoenix with high air-conditioning demand15
Infrastructure: 256 NVIDIA GPUs in an Oracle commercial data center16
Grid conditions: Salt River Project experienced peak demand at 6 p.m.17
Target: Sustained 25% power reduction during grid stress event18
Results
The data center reduced consumption through a 15-minute ramp down, maintained the 25% power reduction over three hours, then ramped back up without exceeding its original baseline consumption.19
"This test was an opportunity to completely reimagine AI data centers as helpful resources to help us operate the power grid more effectively and reliably," said David Rousseau, president of Salt River Project.20
Workload Flexibility Tiers
The demonstration categorized computing workloads into priority tiers:
| Tier | Description | Flexibility |
|---|---|---|
| Flex 1 | Critical jobs | No ability to slow or delay processing |
| Flex 2 | Moderate priority | Some flexibility to delay or adjust processing |
| Flex 3 | Background workloads | Full flexibility to shift processing times21 |
The orchestration software shifted Flex 3 workloads and throttled Flex 2 workloads while protecting Flex 1 operations. AI training jobs proved particularly amenable to scheduling flexibility since completing a training run hours later has minimal business impact compared to real-time inference.22
The Technology Stack
Emerald AI Platform
Emerald Conductor integrates with NVIDIA's AI software stack through several key components:
- GridLink: Receives real-time signals from utilities about grid conditions23
- NVIDIA Mission Control: Coordinates with NVIDIA AI Enterprise components including NIM microservices24
- Workload orchestrator: Manages job prioritization and power allocation across GPU clusters25
This architecture provides the crucial link between the grid's real-time needs and the data center's operational controls, enabling intelligent workload scheduling and power management.26
Alternative Approaches
Verrus (Alphabet spinoff):
Verrus, spun out from Alphabet's Sidewalk Infrastructure Partners, takes a different approach: battery-backed flexibility. The company demonstrated its technology at NREL's 70-MW facility in Colorado.27
| Capability | Specification |
|---|---|
| Response time | Within 10 seconds of utility request28 |
| Load curtailment | Up to 100% within 1 minute29 |
| Battery runtime | Approximately 4 hours on pure battery30 |
| Backup power | BESS replaces diesel generators31 |
"Verrus' technology has the potential to impact how data centers—when intentionally designed for flexibility—can provide meaningful value to grid operators," said Ty Ferretti, Partnership Development Lead at NREL.32
First Verrus facilities are expected in Arizona, California, and Massachusetts, operational by 2026 or 2027.33
The Aurora AI Factory: Reference Implementation
On October 29, 2025, NVIDIA, Emerald AI, EPRI, Digital Realty, and PJM announced the world's first power-flexible AI Factory.34 The 96-MW Aurora AI Factory in Manassas, Virginia, will serve as both the reference implementation and a certification standard for power-flexible AI infrastructure.35
Facility Details
| Specification | Value |
|---|---|
| Capacity | 96 MW |
| Location | Manassas, Virginia |
| Developer | Digital Realty |
| Grid operator | PJM Interconnection |
| Opening | H1 202636 |
Testing Protocol
The Aurora facility will undergo demonstration testing through EPRI's DCFlex Initiative. Testing will simulate:
- Demand spikes during summer heatwaves
- Sudden drops in renewable energy generation
- Real-time responses to grid stress events37
"As the world's demand for AI compute grows, infrastructure innovation must evolve with it. Digital Realty is committed to advancing solutions that integrate compute performance, sustainability, and grid resiliency," said Chris Sharp, CTO of Digital Realty.38
Projected National Impact
The power-flexible reference design, if adopted nationwide, could unlock an estimated 100 GW of capacity on the existing electricity system—equivalent to 20% of total U.S. electricity consumption.39
For context: EPRI studies show data centers could consume 9% of U.S. electricity generation by 2030, more than double current consumption.40 Unlocking 100 GW of flexible capacity would meet projected AI growth for the next decade without requiring extensive new generation or transmission infrastructure.41
Why Skeptics Were Wrong
Traditional arguments against data center flexibility centered on reliability requirements. Hyperscalers promise "five nines" (99.999% uptime) in service-level agreements, leaving little room for power adjustments.42
The Flexibility Math
Analysis from the Energy Institute at Haas revealed a critical insight: grid strain concentrates in a very small number of hours per year. In the vast majority of hours, spare capacity exists to serve new data center loads.43
| Curtailment Tolerance | Unlocked Capacity |
|---|---|
| 0.25% of annual hours (~22 hours) | 76 GW |
| 1% of annual hours (~88 hours) | 126 GW44 |
A steel mill or AI data center that tolerates less than 100 hours of curtailment per year could allow utilities to provide many gigawatts of new capacity without proportionate transmission or generation expansion.45
Workload Realities
The Phoenix demonstration proved that AI workloads contain inherent flexibility that traditional analysis overlooked:
- Training workloads: Not time-sensitive; completing a run hours later has minimal business impact46
- Inference workloads: Some require real-time response, but many batch inference jobs can shift47
- Checkpointing: Brief dips in power during synchronized checkpoints already occur naturally48
"Certain inference workloads in particular may not have flexibility, but training a model is certainly not as time sensitive," noted researchers studying the Phoenix results.49
EPRI DCFlex Initiative: Scaling the Model
EPRI launched the DCFlex initiative in 2024 as a three-year effort to advance understanding of data center demand flexibility and test improvements under real-world conditions.50
Participation
The initiative brings together:
- More than 60 utilities, researchers, hyperscalers, and tech innovators51
- Hyperscalers including Google, Meta, Oracle, and Microsoft52
- Technology companies including NVIDIA53
- Grid operators and equipment suppliers54
Active Demonstrations
| Location | Partners | Focus |
|---|---|---|
| Phoenix, Arizona | Oracle, NVIDIA, Emerald AI, SRP | Computational flexibility during peak demand55 |
| Lenoir, North Carolina | Google, Duke Energy | Workload orchestration for grid support56 |
| Charlotte, North Carolina | Multiple partners | Demand response validation |
| Paris, France | European partners | Power quality response testing57 |
More demonstrations are anticipated throughout 2026.58
Implementation Requirements
For Data Center Operators
Adopting power-flexible operations requires several infrastructure and operational changes:
Software integration:
- Real-time grid signal receivers
- Workload orchestration platforms
- AI-aware scheduling systems59
Operational changes:
- Workload classification by flexibility tier
- SLA modifications to accommodate brief curtailments
- Customer communication about flexibility programs60
No hardware retrofits required: The Phoenix demonstration proved software-only orchestration can achieve meaningful flexibility without energy storage systems or hardware modifications.61
For Utilities
Utilities seeking to integrate data center flexibility must develop:
- Real-time signaling infrastructure to communicate grid conditions
- Tariff structures that incentivize flexible behavior
- Verification and measurement protocols for demand response62
"Data centers are not charities, and they will require incentives to maximize flexibility," noted researchers from Resources for the Future.63
The Grid Investment Reality
Goldman Sachs Research estimates $720 billion of grid spending through 2030 may be needed to accommodate data center growth.64 Transmission projects can take several years to permit and several more to build, creating potential bottlenecks for data center expansion.65
Power-flexible data centers offer an alternative path. Rather than waiting for new generation and transmission capacity, operators can tap existing spare capacity during non-peak hours while curtailing during the limited stress periods.
| Approach | Timeline | Cost | Capacity Added |
|---|---|---|---|
| New transmission | 5-10 years | High | Proportional to investment |
| New generation | 3-7 years | High | Proportional to investment |
| Flexible load integration | 1-2 years | Low | 76-126 GW with modest curtailment66 |
The technology needed for data centers to function as flexible grid assets could be available in the next 1-2 years. The DCFlex Initiative aims to deploy five to ten large-scale flexibility hubs by 2027 that demonstrate how data centers can provide demand flexibility and grid services.67
Introl Perspective
Deploying power-flexible AI infrastructure requires expertise that extends beyond traditional data center construction. The integration of workload orchestration software, real-time grid communication systems, and GPU cluster management demands specialized knowledge across multiple domains.
Introl's coverage area includes 257 locations worldwide with 550 field engineers specializing in high-performance computing and AI infrastructure. This geographic reach and technical depth positions infrastructure partners to support the deployment of flexible AI facilities as the reference design scales from Aurora to national adoption.
Key Takeaways
For Infrastructure Planners
- Power-flexible designs unlock existing grid capacity without waiting for new transmission
- The Aurora reference implementation provides a certification pathway for new facilities
- Software-based flexibility requires no hardware retrofits in existing clusters
For Operations Teams
- Workload classification into flexibility tiers enables intelligent curtailment
- AI training workloads offer significant scheduling flexibility without SLA violations
- Real-time grid signal integration adds operational complexity but unlocks capacity
For Strategic Planners
- 100 GW of potential capacity sits dormant on the existing U.S. grid
- First-mover adoption of flexibility standards may accelerate interconnection timelines
- Utility partnerships increasingly require demonstrated demand response capability
References
-
TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html ↩
-
Emerald AI. "Emerald AI Teams with NVIDIA and Partners to Develop Power-Flexible AI Factory." PR Newswire, October 29, 2025. https://www.prnewswire.com/news-releases/emerald-ai-teams-with-nvidia-and-partners-to-develop-power-flexible-ai-factory-and-reference-design-to-unlock-100-gw-of-grid-capacity-and-supercharge-the-ai-revolution-302597760.html ↩
-
Data Center Dynamics. "Nvidia to deploy Emerald AI's orchestration software at 96MW Aurora data center in Manassas, Virginia." https://www.datacenterdynamics.com/en/news/nvidia-to-deploy-emerald-ais-orchestration-software-at-96mw-aurora-data-center-in-manassas-virginia/ ↩
-
Power Magazine. "Data Centers, the Grid, and the Assumptions That Don't Hold Up." https://www.powermag.com/data-centers-the-grid-and-the-assumptions-that-dont-hold-up/ ↩
-
Data Center Dynamics. "Virginia narrowly avoided power cuts when 60 data centers dropped off the grid at once." https://www.datacenterdynamics.com/en/news/virginia-narrowly-avoided-power-cuts-when-60-data-centers-dropped-off-the-grid-at-once/ ↩
-
GridStatus Blog. "Byte Blackouts: How large data center loads are surfacing new issues." https://blog.gridstatus.io/byte-blackouts-large-data-center-loads-new-issues-pjm/ ↩
-
Rocky Mountain Institute. "Fast, Flexible Solutions for Data Centers." https://rmi.org/fast-flexible-solutions-for-data-centers/ ↩
-
Cardinal News. "Energy demand will outstrip supply in Virginia as data centers proliferate." April 11, 2025. https://cardinalnews.org/2025/04/11/energy-demand-will-outstrip-supply-in-virginia-as-data-centers-proliferate/ ↩
-
Prince William Times. "Data centers expected to spike residential utility bills." https://www.princewilliamtimes.com/news/data-centers-expected-to-spike-electricity-costs/ ↩
-
Utility Dive. "Energy evolution: Meeting the demands of an AI-powered world." https://www.utilitydive.com/news/ai-grid-data-center-epri/807800/ ↩
-
JLARC Virginia. "Data Centers in Virginia." 2024. https://jlarc.virginia.gov/landing-2024-data-centers-in-virginia.asp ↩
-
Bisnow. "Near Misses Instill Fears Over Widespread Data Center-Induced Blackouts." https://www.bisnow.com/national/news/data-center/data-centers-nearly-caused-virginia-blackout-according-to-report-128565 ↩
-
Data Center Dynamics. "Virginia narrowly avoided power cuts when 60 data centers dropped off the grid at once." https://www.datacenterdynamics.com/en/news/virginia-narrowly-avoided-power-cuts-when-60-data-centers-dropped-off-the-grid-at-once/ ↩
-
Power Magazine. "Data Centers Can Be a Flexible Power Load—Here's Why That Matters." https://www.powermag.com/blog/data-centers-can-be-a-flexible-power-load-heres-why-that-matters/ ↩
-
TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html ↩
-
NVIDIA Blog. "How AI Factories Can Help Relieve Grid Stress." https://blogs.nvidia.com/blog/ai-factories-flexible-power-use/ ↩
-
TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html ↩
-
EPRI DCFlex Program. https://dcflex.sf.epri.com/ ↩
-
TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html ↩
-
TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html ↩
-
Power Magazine. "Data Centers Can Be a Flexible Power Load—Here's Why That Matters." https://www.powermag.com/blog/data-centers-can-be-a-flexible-power-load-heres-why-that-matters/ ↩
-
Energy Institute Blog. "Can Data Centers Flex Their Power Demand?" April 14, 2025. https://energyathaas.wordpress.com/2025/04/14/can-data-centers-flex-their-power-demand/ ↩
-
Emerald AI. "Emerald AI Teams with NVIDIA and Partners." https://www.emeraldai.co/blog/launching-the-first-power-flexible-ai-factory-with-nvidia ↩
-
NVIDIA Resources. "Emerald AI Orchestrates AI Factories to Help Relieve Grid Stress." https://resources.nvidia.com/en-us-energy-utilities/ai-factories-flexible ↩
-
Latitude Media. "How the world's first flexible AI factory will work in tandem with the grid." https://www.latitudemedia.com/news/how-the-worlds-first-flexible-ai-factory-will-work-in-tandem-with-the-grid/ ↩
-
Emerald AI. "Emerald AI Teams with NVIDIA and Partners." PR Newswire. https://www.prnewswire.com/news-releases/emerald-ai-teams-with-nvidia-and-partners-to-develop-power-flexible-ai-factory-and-reference-design-to-unlock-100-gw-of-grid-capacity-and-supercharge-the-ai-revolution-302597760.html ↩
-
Latitude Media. "Verrus successfully demos its flexible data center technology." https://www.latitudemedia.com/news/verrus-successfully-demos-its-flexible-data-center-technology/ ↩
-
Verrus. "Verrus Demonstrates Industry Leading Grid-Interactive Data Center Technology at Scale, in Collaboration with NREL." https://verrusdata.com/news/verrus-nrel ↩
-
Volts. "Can data centers be good grid citizens?" https://www.volts.wtf/p/can-data-centers-be-good-grid-citizens ↩
-
Latitude Media. "The data center of the future looks like a massive virtual power plant." https://www.latitudemedia.com/news/the-data-center-of-the-future-looks-like-a-massive-virtual-power-plant/ ↩
-
TechCrunch. "Alphabet spin-off SIP launches Verrus, a data center concept built around battery 'microgrids'." March 11, 2024. https://techcrunch.com/2024/03/11/sip-verrus-data-center/ ↩
-
Verrus. "Verrus Demonstrates Industry Leading Grid-Interactive Data Center Technology at Scale, in Collaboration with NREL." https://verrusdata.com/news/verrus-nrel ↩
-
Latitude Media. "A status update on data center flexibility." https://www.latitudemedia.com/news/a-status-update-on-data-center-flexibility/ ↩
-
American Public Power Association. "NVIDIA, Emerald AI, EPRI, PJM and Others to Develop Power-Flexible AI Factory." https://www.publicpower.org/periodical/article/nvidia-emerald-ai-epri-pjm-and-others-develop-power-flexible-ai-factory ↩
-
Emerald AI. "Emerald AI Teams with NVIDIA and Partners." https://www.emeraldai.co/blog/launching-the-first-power-flexible-ai-factory-with-nvidia ↩
-
Data Center Dynamics. "Nvidia to deploy Emerald AI's orchestration software at 96MW Aurora data center in Manassas, Virginia." https://www.datacenterdynamics.com/en/news/nvidia-to-deploy-emerald-ais-orchestration-software-at-96mw-aurora-data-center-in-manassas-virginia/ ↩
-
Latitude Media. "How the world's first flexible AI factory will work in tandem with the grid." https://www.latitudemedia.com/news/how-the-worlds-first-flexible-ai-factory-will-work-in-tandem-with-the-grid/ ↩
-
Emerald AI. "Emerald AI Teams with NVIDIA and Partners." PR Newswire. https://www.prnewswire.com/news-releases/emerald-ai-teams-with-nvidia-and-partners-to-develop-power-flexible-ai-factory-and-reference-design-to-unlock-100-gw-of-grid-capacity-and-supercharge-the-ai-revolution-302597760.html ↩
-
Yahoo Finance. "Emerald AI Teams with NVIDIA and Partners to Develop Power-Flexible AI Factory." https://finance.yahoo.com/news/emerald-ai-teams-nvidia-partners-093000156.html ↩
-
EPRI. "Data Center Flexible Load Initiative." https://www.epri.com/about/media-resources/press-release/yimzJV2Xnv9cqiZTaU1zxBeDlEtwYQk1 ↩
-
Utility Dive. "EPRI launches data center flexibility initiative with utilities, Google, Meta, NVIDIA." https://www.utilitydive.com/news/epri-launches-data-center-flexibility-initiative-with-NVIDIA-google-meta/731490/ ↩
-
Energy Institute Blog. "Can Data Centers Flex Their Power Demand?" April 14, 2025. https://energyathaas.wordpress.com/2025/04/14/can-data-centers-flex-their-power-demand/ ↩
-
Energy Institute Blog. "Can Data Centers Flex Their Power Demand?" April 14, 2025. https://energyathaas.wordpress.com/2025/04/14/can-data-centers-flex-their-power-demand/ ↩
-
Rocky Mountain Institute. "Fast, Flexible Solutions for Data Centers." https://rmi.org/fast-flexible-solutions-for-data-centers/ ↩
-
Resources for the Future. "The Hype on Hyperscalers: Data Centers and Growing Electricity Demand." https://www.resources.org/common-resources/the-hype-on-hyperscalers-data-centers-and-growing-electricity-demand/ ↩
-
Energy Institute Blog. "Can Data Centers Flex Their Power Demand?" April 14, 2025. https://energyathaas.wordpress.com/2025/04/14/can-data-centers-flex-their-power-demand/ ↩
-
Latitude Media. "The mechanics of data center flexibility." https://www.latitudemedia.com/news/catalyst-the-mechanics-of-data-center-flexibility/ ↩
-
Energeia USA. "The Future of Data Center Electrical Grid Impacts." https://energeia-usa.com/data-center-grid-impacts/ ↩
-
Energy Institute Blog. "Can Data Centers Flex Their Power Demand?" April 14, 2025. https://energyathaas.wordpress.com/2025/04/14/can-data-centers-flex-their-power-demand/ ↩
-
EPRI. "DCFlex: Data Center Flexible Load Initiative." https://www.epri.com/research/products/000000003002031004 ↩
-
Utility Dive. "Energy evolution: Meeting the demands of an AI-powered world." https://www.utilitydive.com/news/ai-grid-data-center-epri/807800/ ↩
-
Utility Dive. "EPRI launches data center flexibility initiative with utilities, Google, Meta, NVIDIA." https://www.utilitydive.com/news/epri-launches-data-center-flexibility-initiative-with-NVIDIA-google-meta/731490/ ↩
-
EPRI DCFlex. https://dcflex.sf.epri.com/ ↩
-
EPRI Journal. "Flexible Loads, Resilient Grids." https://eprijournal.com/flexible-loads-resilient-grids/ ↩
-
Power Magazine. "Data Centers Can Be a Flexible Power Load—Here's Why That Matters." https://www.powermag.com/blog/data-centers-can-be-a-flexible-power-load-heres-why-that-matters/ ↩
-
EPRI Journal. "Flexible Loads, Resilient Grids." https://eprijournal.com/flexible-loads-resilient-grids/ ↩
-
EPRI Journal. "Flexible Loads, Resilient Grids." https://eprijournal.com/flexible-loads-resilient-grids/ ↩
-
Utility Dive. "Energy evolution: Meeting the demands of an AI-powered world." https://www.utilitydive.com/news/ai-grid-data-center-epri/807800/ ↩
-
NVIDIA Blog. "How AI Factories Can Help Relieve Grid Stress." https://blogs.nvidia.com/blog/ai-factories-flexible-power-use/ ↩
-
Utility Dive. "Mainstreaming AI data center flexibility." https://www.utilitydive.com/news/mainstreaming-ai-data-center-flexibility/804103/ ↩
-
TechXplore. "AI data centers could stabilize the power grid." January 2026. https://techxplore.com/news/2026-01-ai-centers-stabilize-power-grid.html ↩
-
Renewable Energy World. "As AI and data center power demand skyrockets, flexible load integration becomes a critical strategy for utilities." https://www.renewableenergyworld.com/power-grid/grid-modernization/as-ai-and-data-center-power-demand-skyrockets-flexible-load-integration-becomes-a-critical-strategy-for-utilities/ ↩
-
Resources for the Future. "The Hype on Hyperscalers: Data Centers and Growing Electricity Demand." https://www.resources.org/common-resources/the-hype-on-hyperscalers-data-centers-and-growing-electricity-demand/ ↩
-
Goldman Sachs. "AI to drive 165% increase in data center power demand by 2030." https://www.goldmansachs.com/insights/articles/ai-to-drive-165-increase-in-data-center-power-demand-by-2030 ↩
-
Goldman Sachs. "AI to drive 165% increase in data center power demand by 2030." https://www.goldmansachs.com/insights/articles/ai-to-drive-165-increase-in-data-center-power-demand-by-2030 ↩
-
Rocky Mountain Institute. "Fast, Flexible Solutions for Data Centers." https://rmi.org/fast-flexible-solutions-for-data-centers/ ↩
-
Data Center Knowledge. "2026 Predictions: AI Sparks Data Center Power Revolution." https://www.datacenterknowledge.com/operations-and-management/2026-predictions-ai-sparks-data-center-power-revolution ↩