Five years. The average time for a data center project to navigate the U.S. grid interconnection queue has grown from under two years in 2008 to nearly five years today, with California projects stretching beyond nine years.1 Senator Tom Cotton introduced the Decentralized Access to Technology Alternatives (DATA) Act on January 8, 2026, proposing a bypass: exempt data centers that build their own off-grid power infrastructure from Federal Energy Regulatory Commission (FERC) oversight entirely.2 For infrastructure operators facing 2,600 GW of projects stuck in interconnection queues, the legislation offers a potential path to deployment that circumvents the primary bottleneck constraining AI infrastructure scaling.
TL;DR
The DATA Act creates a new utility category called "consumer-regulated electric utilities" (CREUs) that exempts facilities completely disconnected from the main grid from Federal Power Act provisions, including FERC rate regulation, reliability standards, interconnection rules, and transmission planning.3 Companies building off-grid power systems would avoid interconnection studies and upgrade requirements that currently add 4-6 years to project timelines.4 The exemption ends immediately upon grid connection, and environmental and zoning requirements remain in force.5 Similar legislation passed in New Hampshire in 2025, providing a state-level precedent for the federal approach.6
The Interconnection Crisis: Why Off-Grid Matters
Understanding the DATA Act requires recognizing the scale of the interconnection bottleneck constraining data center development.
Queue Backlog Statistics
| Metric | Value | Trend |
|---|---|---|
| Total U.S. queue backlog | 2,600+ GW | 2x current installed capacity |
| Average wait time (2024) | ~5 years | Up from <2 years in 2008 |
| California worst case | 9+ years | Regional extremes |
| Northern Virginia | 7 years | Primary data center market |
| Project success rate (2000-2018) | 20% | 80% fail to reach operation |
Sources: Berkeley Lab1, Wood Mackenzie7, ENR8
Only 20% of projects requesting interconnection between 2000 and 2018 ever reached commercial operation.1 The completion rate has worsened as queue volumes have grown. Over 2,000 GW of projects remain stuck in interconnection queues across ISOs and RTOs.9
Regional Queue Status
| Grid Operator | Backlog | 2026 Study Pipeline | Key Constraint |
|---|---|---|---|
| PJM | 60+ GW | Under active study | Study processing capacity |
| MISO | 170+ GW | 4+ year delays | Solar/wind/storage heavy |
| ERCOT | 8 GW large load requests | 700% increase 2023-2024 | Rapid demand growth |
| CAISO | Worst completion rates | 9+ year timelines | State policy complexity |
Sources: Zero Emission Grid10, CTVC11, CenterPoint Energy12
ERCOT saw a 700% spike in large load interconnection requests from 2023 to 2024, with CenterPoint Energy reporting growth from 1 GW to 8 GW in late 2023 to late 2024.12 The Texas market's relative speed still leaves projects facing multi-year timelines.
DATA Act Provisions: What the Bill Does
The legislation creates regulatory carve-outs for fully isolated power systems serving data centers and other energy-intensive industrial loads.
Key Definitions
| Term | Definition | Implication |
|---|---|---|
| Consumer-Regulated Electric Utility (CREU) | Off-grid power system serving new loads | New regulatory category |
| Fully isolated | No connection to traditional grid | Exemption trigger |
| New electric loads | Loads not previously served | Prevents existing load diversion |
Regulatory Exemptions
| Current Requirement | Status Under DATA Act | Impact |
|---|---|---|
| FERC rate regulation | Exempt | Private pricing |
| Reliability standards | Exempt | Self-determined standards |
| Interconnection rules | Exempt | No queue process |
| Transmission planning | Exempt | No upgrade cost allocation |
| Merger approval | Exempt | M&A flexibility |
| Environmental/zoning laws | Still apply | No environmental bypass |
CREUs would also receive exemptions from the Public Utility Regulatory Policies Act and the Public Utility Holding Company Act.5 The exemptions end immediately if a CREU connects to the grid, preventing hybrid arrangements that might cherry-pick regulatory benefits.
Comparison to State Precedent
| Jurisdiction | Legislation | Status | Scope |
|---|---|---|---|
| New Hampshire | Off-grid exemption | Signed 2025 | State utility laws |
| Federal (proposed) | DATA Act 2026 | Introduced Jan 8, 2026 | Federal Power Act |
| ALEC model | Model legislation | Released Jan 2026 | Template for states |
New Hampshire's Republican Governor Kelly Ayotte signed legislation in 2025 exempting off-grid power providers from state utility laws.6 The American Legislative Exchange Council (ALEC) released model state legislation in January 2026 following Cotton's federal bill introduction.14
FERC's Parallel Regulatory Track
While Cotton's bill proposes bypassing FERC, the commission has pursued its own reforms to address data center interconnection.
December 2025 FERC Order
| Action | Requirement | Deadline |
|---|---|---|
| PJM tariff revisions | Generation interconnection procedures | January 20, 2026 |
| New transmission services | Firm/Non-Firm Contract Demand | Briefs due Feb 16, 2026 |
| Response deadline | Industry comments | March 18, 2026 |
| Reply deadline | Final arguments | April 17, 2026 |
On December 19, 2025, FERC directed PJM to reform its tariff for co-located generation and load, finding the existing tariff "unjust and unreasonable" due to lack of clarity in rates and terms applying to interconnection customers.15 The commission proposed two new transmission services based on net withdrawals rather than gross load.17
DOE Directive to FERC
| Directive Element | Requirement | Timeline |
|---|---|---|
| Rulemaking initiation | Accelerate large load interconnection | Immediate |
| Joint filing option | Co-located load and generation requests | New procedure |
| Study time reduction | Shortened timelines | TBD by April 2026 |
| Grid update cost reduction | Lower participant funding | Under consideration |
Source: DOE Letter, White & Case18
On October 23, 2025, DOE instructed FERC to initiate rulemaking to "rapidly accelerate the interconnection of large loads" by April 30, 2026.18 The directive would enable customers to file joint, co-located load and generation interconnection requests directly to FERC.
Current FERC Funding Model
| Cost Element | Current Allocation | Industry Position |
|---|---|---|
| Network upgrades | 100% participant funded | High barrier |
| Study costs | Participant funded | Queue deterrent |
| Timeline | 4-6 years typical | Project viability threat |
Source: ENR8
FERC's 100% participant funding model requires large load customers to pay the full cost of grid network upgrades, creating significant financial barriers beyond the timeline challenges.8
Behind-the-Meter Alternative: Current Market
The DATA Act codifies and expands options already emerging through behind-the-meter (BTM) power arrangements.
BTM Market Scale
| Metric | Value | Source |
|---|---|---|
| Projected BTM data center power by 2030 | 35+ GW | Boston Consulting Group |
| Current power shortage | 45+ GW | BCG estimate |
| Active interconnection requests | 12,000+ projects | Queue data |
| Requested capacity (generation) | 1,570 GW | Queue aggregate |
| Requested capacity (storage) | 1,030 GW | Queue aggregate |
Source: BCG via S&P Global19, Data Center Knowledge20
More than 35 GW of data center power will be self-generated by 2030, according to Boston Consulting Group analysis.19 The projection reflects developers' rational response to queue timelines that exceed typical data center construction periods of 12-18 months.21
BTM Technology Options
| Technology | Typical Capacity | Permitting Timeline | Grid Dependency |
|---|---|---|---|
| Natural gas reciprocating engines | Up to 20 MW per unit | Minor source air permit | None |
| Modular gas platforms | Up to 200 MW combined | Minor source permit | None |
| Fuel cells | Scalable | Fast deployment | None |
| SMRs | Up to 300 MW | NRC licensing required | None |
| On-site solar + storage | Variable | State-dependent | Optional backup |
Sources: VoltaGrid22, NuScale23, S&P Global19
VoltaGrid's Qpac modular platform uses reciprocating engine generators producing up to 20 MW each, combinable to 200 MW under minor source air permits.22 Fuel cells provide fast deployment timelines compared to traditional generation, serving as "bridge" resources during grid connection waits.19
SMR Potential Under DATA Act
| SMR Developer | Capacity | Data Center Deals | Status |
|---|---|---|---|
| NuScale | 77 MW per module | Multiple announced | NRC certified |
| X-Energy | 80 MW per module | Amazon partnership | Pre-licensing |
| Kairos Power | 75 MW thermal | Google partnership | Demo phase |
| TerraPower | 345 MW | Multiple discussions | Construction starting |
Sources: Deloitte24, Last Energy25, EIA26
SMRs represent a strong potential match for AI data center energy demands. On-site SMRs allow operators to bypass long grid interconnection queues and secure dedicated, non-stop power supply.25 Because SMRs deploy in modular increments, they can scale alongside AI campuses as compute demand increases.
Political and Industry Reactions
The DATA Act has generated predictable support and opposition along utility versus developer lines.
Supporter Arguments
| Argument | Proponent | Basis |
|---|---|---|
| Protects ratepayers | Senator Cotton | Off-grid doesn't affect grid rates |
| Accelerates AI | Tech industry | Bypasses 5-year queues |
| Enables innovation | Deregulation advocates | Removes federal barriers |
| Arkansas protection | Cotton | Local rate concerns |
Sources: Cotton Press Release27, Arkansas Democrat-Gazette28
"Data centers suck up a huge amount of electricity, in some cases as much as small towns. If that electricity is just coming from the power generation we have on the grid that is powering our homes and our farms and our factories and our business places, then of course there's going to be a price spike," Cotton stated.29
Opponent Arguments
| Argument | Proponent | Basis |
|---|---|---|
| Revenue threat | Electric utilities | Loss of large customers |
| Cost shifting | Consumer advocates | Fixed costs onto residential |
| Reliability concerns | Grid operators | Reduced system resources |
| Environmental gaps | Some critics | No grid-scale planning |
Sources: Utility Dive13, Arkansas Times30
Critics argue that if the legislation succeeds in luring large loads off the grid into bilateral agreements, fixed costs could shift onto residential and small business customers.13 Most providers and customers want grid backup, limiting the bill's practical applicability.6
State Actions
| State | Action | Status | Approach |
|---|---|---|---|
| Virginia | Special rates for data centers | Enacted | Rate design |
| Texas | SB6 flexibility requirements | Enacted | Demand response mandate |
| New Hampshire | Off-grid exemption | Signed 2025 | Regulatory carve-out |
| Ohio | Under consideration | Pending | TBD |
Source: MultiState31
Texas Senate Bill 6 requires new loads over 75 MW connecting to ERCOT to be flexible and participate in demand response, representing the opposite regulatory philosophy from Cotton's bill.31
Infrastructure Planning Implications
The DATA Act creates strategic options for operators regardless of whether it passes.
Project Timeline Comparison
| Approach | Typical Timeline | Regulatory Risk | Capital Requirement |
|---|---|---|---|
| Traditional grid connection | 5-7 years | Queue position dependent | Upgrade cost sharing |
| Behind-the-meter (current) | 18-36 months | State permitting | Self-funded generation |
| Under DATA Act (if passed) | 12-24 months | Federal exemption | Self-funded generation |
| Co-location (FERC reform) | 2-4 years | PJM compliance | Upgrade cost sharing |
Estimates based on industry analysis820
Power Source Economics
| Source | Capex ($/kW) | Opex ($/MWh) | Availability | DATA Act Compatible |
|---|---|---|---|---|
| Grid connection | Variable | $45-80 | 99.9%+ | N/A |
| Natural gas BTM | $800-1,200 | $35-55 | 95-99% | Yes |
| SMR | $6,000-10,000 | $25-40 | 90-95% | Yes |
| Solar + storage | $2,500-4,000 | $0-15 | 85-95% | Yes |
Industry estimates, variable by project242532
Grid connections offer highest availability but longest timelines. Natural gas BTM provides fastest deployment with proven technology. SMRs offer lowest operating costs long-term but highest capital requirements and longest deployment timelines among off-grid options.
Data Center Pipeline Exposure
| Metric | Value | Implication |
|---|---|---|
| Projects targeting 2026 operation | 105 projects, 8.9 GW | Near-term capacity |
| Projects under construction | 47 projects | Most likely to deliver |
| Typical construction time | 12-18 months | Power is constraint |
| At-risk projects | ~58 projects | Dependent on power timing |
Source: CTVC11
Over 8.9 GW across 105 data center projects target operation by end-2026, with 47 already under construction.11 Since data centers themselves only take 12-18 months to build, power availability determines whether projects come online on time.
Strategic Recommendations
Introl's 257 global locations position infrastructure teams to evaluate both traditional and alternative power approaches as regulatory frameworks evolve.
For Infrastructure Planners
Evaluate project portfolios against both FERC reform timelines (April 2026 deadline for large load rule) and DATA Act passage probability. Projects with 3+ year horizons may benefit from hybrid strategies that preserve grid backup options while pursuing BTM acceleration. Natural gas BTM provides lowest-risk bridge to grid connection or SMR availability.
For Operations Teams
Monitor state-level legislation following the ALEC model template. States with existing data center concentrations (Virginia, Texas, Ohio) face the most immediate pressure to clarify off-grid regulatory status. Operational flexibility to support both grid-connected and islanded modes increases optionality as regulations crystallize.
For Strategic Decision-Makers
The DATA Act's introduction signals bipartisan recognition that current interconnection timelines threaten U.S. AI infrastructure competitiveness. Regardless of the bill's fate, the regulatory trajectory favors operators who can deploy power independently of grid constraints. Capital allocation should prioritize projects with multiple power pathway options.
Key Takeaways
Regulatory Landscape
The DATA Act proposes the most significant change to federal utility regulation since FERC's formation. The bill's CREU category would create a parallel power system exempt from rules designed for grid-integrated utilities. Even if the legislation fails, its introduction influences FERC's ongoing reform proceedings and state-level policy development.
Timeline Implications
Current 5-year interconnection queues make traditional grid connection incompatible with AI infrastructure deployment timelines. Behind-the-meter options reduce deployment to 18-36 months currently, with potential further acceleration under DATA Act exemptions. Projects requiring 2026-2027 operation should pursue BTM strategies regardless of regulatory outcome.
Cost Structure Evolution
Off-grid approaches shift cost structures from shared upgrade contributions to self-funded capital expenditure. Operators with strong balance sheets gain competitive advantage in securing power capacity through direct generation investment. Smaller operators may face increasing cost disadvantages as large loads exit shared grid infrastructure.
References
-
Land Values by Acres. "Part 4: How Interconnection Queues Are Stalling Data Center Growth." Acres. 2026. https://landvalues.acres.com/part-4-interconnection-queues-stalling-data-center-growth ↩↩↩
-
Data Center Dynamics. "US Senator proposes bill permitting AI data centers to bypass federal power rules via off-grid energy infrastructure development." DCD. January 2026. https://www.datacenterdynamics.com/en/news/us-senator-proposes-bill-permitting-ai-data-centers-to-bypass-federal-power-rules-via-off-grid-energy-infrastructure-development/ ↩↩
-
Utility Dive. "Senate bill exempts fully isolated large loads from FERC, DOE regulation." Utility Dive. January 2026. https://www.utilitydive.com/news/senate-bill-exempts-fully-isolated-large-loads-from-ferc-doe-regulation/809330/ ↩↩
-
MeriTalk. "Sen. Cotton Pushes Off-Grid Power Plan for AI Data Centers." MeriTalk. January 2026. https://www.meritalk.com/articles/sen-cotton-pushes-off-grid-power-plan-for-ai-data-centers/ ↩
-
Senator Tom Cotton. "Cotton Introduces Bill to Lower Energy Costs for Arkansans." U.S. Senator Cotton of Arkansas. January 8, 2026. https://www.cotton.senate.gov/news/press-releases/cotton-introduces-bill-to-lower-energy-costs-for-arkansans ↩↩↩
-
Reason. "Data centers use lots of electricity. This bill would let them go off the grid." Reason. January 12, 2026. https://reason.com/2026/01/12/data-centers-use-lots-of-electricity-this-bill-would-let-them-go-off-the-grid/ ↩↩↩↩
-
Wood Mackenzie. "5 key questions about US grid interconnection answered." Wood Mackenzie. 2026. https://www.woodmac.com/news/opinion/5-key-questions-about-us-grid-interconnection-answered/ ↩
-
Engineering News-Record. "Grid Access, Not Land, Emerges as Bottleneck for Data Center Construction." ENR. 2026. https://www.enr.com/articles/62227-grid-access-not-land-emerges-as-bottleneck-for-data-center-construction ↩↩↩↩
-
Global Data Center Hub. "The Interconnection Bottleneck: How Renewable Approval Backlogs Are Repricing the Energy-to-Data Center Equation." Global Data Center Hub. 2026. https://www.globaldatacenterhub.com/p/the-interconnection-bottleneck-how ↩
-
Zero Emission Grid. "Clean Energy Interconnection Backlog—2025 Trends & Insights." Zero Emission Grid. 2025. https://www.zeroemissiongrid.com/insights-press-zeg-blog/interconnection-backlog/ ↩
-
CTVC. "The data center report we promise you haven't read." CTVC. 2026. https://www.ctvc.co/the-data-center-report-we-promise-you-havent-read/ ↩↩↩
-
CenterPoint Energy via ENR. "Power Sector Debates New Federal Rules for Data Center 'Large Load' Links to Grid." ENR. 2026. https://www.enr.com/articles/62219-power-sector-debates-new-federal-rules-for-data-center-large-load-links-to-grid ↩↩
-
Utility Dive. "Senate bill exempts fully isolated large loads from FERC, DOE regulation." Utility Dive. January 2026. https://www.utilitydive.com/news/senate-bill-exempts-fully-isolated-large-loads-from-ferc-doe-regulation/809330/ ↩↩↩
-
MeriTalk. "Deregulation, Data Centers, and Dominance: Washington's AI Wrapped." MeriTalk. January 2026. https://meritalk.com/articles/deregulation-data-centers-and-dominance-washingtons-ai-wrapped/ ↩↩
-
FERC. "FERC Directs Nation's Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers." FERC. December 2025. https://www.ferc.gov/news-events/news/ferc-directs-nations-largest-grid-operator-create-new-rules-embrace-innovation-and ↩↩
-
K&L Gates. "FERC Orders PJM to Reform Tariff for Co-Located Generation and Load." K&L Gates HUB. January 15, 2026. https://www.klgates.com/FERC-Orders-PJM-to-Reform-Tariff-for-Co-Located-Generation-and-Load-1-15-2026 ↩
-
Gibson Dunn. "FERC Orders PJM, Largest U.S. Grid Operator, to Revise Tariff to Permit New Transmission Services for Co-Located Loads Such as Data Centers." Gibson Dunn. January 2026. https://www.gibsondunn.com/ferc-orders-pjm-largest-u-s-grid-operator-to-revise-tariff-to-permit-new-transmission-services-for-co-located-loads-such-as-data-centers/ ↩
-
White & Case. "DOE directs FERC to accelerate interconnection of data centers." White & Case. October 2025. https://www.whitecase.com/insight-alert/doe-directs-ferc-accelerate-interconnection-data-centers ↩↩
-
S&P Global. "Data center developers turn to distributed behind-the-meter power." S&P Global Market Intelligence. October 2025. https://www.spglobal.com/market-intelligence/en/news-insights/articles/2025/10/data-center-developers-turn-to-distributed-behind-the-meter-power-94174247 ↩↩↩↩
-
Data Center Knowledge. "Data Centers Bypassing the Grid to Obtain the Power They Need." Data Center Knowledge. 2026. https://www.datacenterknowledge.com/energy-power-supply/data-centers-bypassing-the-grid-to-obtain-the-power-they-need ↩↩
-
CTVC. "The data center report we promise you haven't read." CTVC. 2026. https://www.ctvc.co/the-data-center-report-we-promise-you-havent-read/ ↩
-
Gas Turbine World. "Data Center developers bypassing grid to obtain power." Gas Turbine World. 2026. https://gasturbineworld.com/behind-the-meter-data-centers/ ↩↩
-
NuScale Power. "Small Modular Reactor (SMR) Nuclear Technology." NuScale Power. https://www.nuscalepower.com/ ↩
-
Deloitte. "Nuclear energy's role in powering data center growth." Deloitte. 2026. https://www.deloitte.com/us/en/insights/industry/power-and-utilities/nuclear-energy-powering-data-centers.html ↩↩
-
Last Energy. "On-Site Nuclear Power: SMRs Create New Opportunities for Colocation Data Centers." Last Energy. 2026. https://www.lastenergy.com/blog/smrs-colocation-data-centers ↩↩↩
-
EIA. "Data center owners turn to nuclear as potential electricity source." U.S. Energy Information Administration. 2025. https://www.eia.gov/todayinenergy/detail.php?id=63304 ↩
-
Senator Tom Cotton. "Cotton Introduces Bill to Lower Energy Costs for Arkansans." U.S. Senator Cotton of Arkansas. January 8, 2026. https://www.cotton.senate.gov/news/press-releases/cotton-introduces-bill-to-lower-energy-costs-for-arkansans ↩
-
Arkansas Democrat-Gazette via KATV. "Cotton introduces bill to shield Arkansans from data center-driven electric rate hikes." KATV. January 2026. https://katv.com/news/local/cotton-introduces-bill-to-shield-arkansans-from-data-center-driven-electric-rate-hi-artificial-intelligence-ai-entergy-senator-tom-cotton-trump-electric-bill-power-plant-google-avaio-little-rock-meta-aws-public-service-commission-danni-hoefer-data-act ↩
-
KATV. "Cotton introduces bill to shield Arkansans from data center-driven electric rate hikes." KATV. January 2026. https://katv.com/news/local/cotton-introduces-bill-to-shield-arkansans-from-data-center-driven-electric-rate-hi-artificial-intelligence-ai-entergy-senator-tom-cotton-trump-electric-bill-power-plant-google-avaio-little-rock-meta-aws-public-service-commission-danni-hoefer-data-act ↩
-
Arkansas Times. "Shoffner blasts Cotton over his DATA Act to deregulate energy for data centers." Arkansas Times. January 13, 2026. https://arktimes.com/arkansas-blog/2026/01/13/shoffner-blasts-cotton-over-his-data-act-to-deregulate-energy-for-data-centers ↩
-
MultiState. "How States Will Power the Trillion-Dollar Data Center Rush." MultiState. October 2025. https://www.multistate.us/insider/2025/10/8/how-states-will-power-the-trillion-dollar-data-center-rush ↩↩
-
Orrick. "Powering Data Centers." Megawatts to Megabytes: Orrick's Guide to Developing, Financing & Powering Data Centers. November 2025. https://www.orrick.com/en/Insights/2025/11/Powering-Data-Centers ↩
-
The Hill. "DATA Act of 2026: A solution for data center power." The Hill. January 2026. https://thehill.com/opinion/energy-environment/5707456-data-act-reform-grid/ ↩
-
Woodway Energy. "Bridging the 5-Year Gap: Off-Grid and Behind-the-Meter Gas Power Generation for Data Centers." Woodway Energy. 2026. https://www.woodwayenergy.com/off-grid-btm-gas-power-generation-data-centers/ ↩
-
Eaton. "Beyond the grid data center power." Eaton. 2026. https://www.eaton.com/us/en-us/company/news-insights/blog/beyond-the-grid-data-center-power.html ↩
-
Morgan Lewis. "Failure to Connect: Grid Challenges Persist as Demand Rises." Morgan Lewis. July 2025. https://www.morganlewis.com/pubs/2025/07/failure-to-connect-grid-challenges-persist-as-demand-rises ↩
-
Camus Energy. "Why Does It Take So Long to Connect a Data Center to the Grid?" Camus Energy. 2026. https://www.camus.energy/blog/why-does-it-take-so-long-to-connect-a-data-center-to-the-grid ↩
-
University of Chicago. "How the Interconnection Queue Backlog Is Slowing Energy Growth." Sustainability Dialogue. 2026. https://sustainabilitydialogue.uchicago.edu/news/how-the-interconnection-queue-backlog-is-slowing-energy-growth/ ↩
-
Data Center Knowledge. "Data Center Compliance in 2026: What Changed, What's Next." Data Center Knowledge. 2026. https://www.datacenterknowledge.com/compliance/data-center-compliance-in-2026-what-changed-what-s-next-and-how-to-prepare ↩
-
Bipartisan Policy Center. "Strategic Federal Actions Aim to Strengthen AI and Energy Infrastructure." Bipartisan Policy Center. 2026. https://bipartisanpolicy.org/explainer/strategic-federal-actions-aim-to-strengthen-ai-and-energy-infrastructure/ ↩